Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 679 NW BLACKBERRY CIR
LAKE CITY, FL 32055
Parcel #: 02168-105
Acres: 4.02
Owner: Crosby Marcella D
Subdivision: Blackberry Farms
Zoning: PRRD
Flood Zone: X
District: 3
Application #: 45912
Permit #: 000039661
Related Permit: Culvert: 000039660
Submitted:
Issued: Thursday, April 23, 2020
Expires: Tuesday, January 12, 2021
Completed: Tuesday, January 12, 2021
Status: Completed
Septic Release? Yes
Notes:
MEETS 200' BUFFER REQUIREMENT, SUBDIVISION PLAT SHOWS A 20' DRAINAGE EASEMENT OFF BLACKBERRY CIRCLE DIAGONAL AT THE NORHT EDGE OF THIS LOT ENGINEER LETTER REC'D - STATING THAT AT THE BUILDING SITE THE MINIMUM FLOOR ELEVATION SHALL BE 106.8' AND ABOVE THE HIGHEST NATURAL GRADE AND ANY DISTURBED AREA AROUND THE STRUCTURE SHALL BE GRADED TO DIRECT ALL RUNOFF TO THE SOUTHEAST TO A NATURAL LOW AREA. SURVEYOR ELEVATION LETTER REC'D - THE MAIN FLOOR ELEVATION IS 106.8'.
Job Details
Finished floor requirement
Fema map number 12023C0480C
Type Roofing Job Replacement - Tear off Existing and Replace
Further Job Details (Explain if decking is being replaced and or Repairs are being done.) Tear off existing roof and install new asphalt shingles
Type of structure House
Commercial or Residential Residential
Roof Area (for this job) Sq Ft 3000
No. of Stories 1
Roof Pitch 4:12 or Greater
Is the existing roof being removed? Yes
Type of New Roofing Product Asphalt Shingles
Florida Product Approval Number FL16305-R13
Product Manufacturer Atlas Roofing Corporation
Product Description Fiberglass Reinforced Laminated
Building Code Edition 2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Sealed roof decking options: (Must select an option.) a self-adhering polymer-modified bitumen underlayment complying with ASTM D1970 applied over the entire roof.
Ventilation: Ridge Vent
Flashing: Replace All
Drip Edge: Repair Existing
Valley Treatment: New Mineral Surface
Any cable and/or race-way wiring located on or within the roof assembly? No
Review Notes
4/6/2020 Application pending.
4/20/2020 Point Review - Received
4/20/2020 Zoning Review - Completed/Sent for Final Review
4/23/2020 Permit Issued Permit #000039661 created and approved.
10/7/2020 Final Review - Payment Needed
Contractors
Name/ Business License Title Role
Josh Sparks
Sparks Construction
CBC1252260 Building Contractor Contractor
Benjamin L Sparks
Line Electric Company, Llc
EC13009101 Cert. Electrical Subcontractor
Stephen M Brisbois
Epic Ac Service
CAC1819412 Cert. A/c Class “b” Subcontractor
Cody Barrs
Barrs Plumbing,inc.
CFC1427145 Plumbing Contractor Subcontractor
Ralph W Laverdure
Rwl Roofing,llc.
CCC1328590 Roofing Contractor Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Matt Forsyth 4/29/2020
Passed: Engineering - Setbacks Need Portalet For Next Inspection Matt Forsyth 4/29/2020
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 5/18/2020
Passed: Building - Slab Troy Crews 5/26/2020
Failed: Building - Roof Decking Cover But Remove Shiners And Look Again At Framing Tommy Matthews 6/30/2020
Failed: Building - Wall Sheathing Remove And Replace Shiners. Tommy Matthews 6/30/2020
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 7/16/2020
Failed: Building - Framing All Headers Nailed 12"on Center Top And Bottom. Matt Forsyth 7/16/2020
Passed: Building - Roof Decking Matt Forsyth 7/16/2020
Passed: Building - Strapping Matt Forsyth 7/16/2020
Failed: Building - Framing Beams On Porch And Lvl In Garage Nailed 12" Oc Both Sides Top And Bottom (face).anchor Bolt Nut Missing In Garage.need Safety Railing On Staircase. Matt Forsyth 8/20/2020
Failed: Electrical - 2nd Rough-In Need Nail Plates In Following Areas;service Entrance,double Oven,hall Bath Matt Forsyth 8/20/2020
Passed: Mechanical - Rough In Matt Forsyth 8/20/2020
Failed: Plumbing/Gas - 2nd Rough-In Nail Plates For Gas And Waste Pipe In Kitchen Master Bath And Entry. Water On Waste Pipe Notied Will It Hold In Bathtub?(second Floor) Matt Forsyth 8/20/2020
Passed: Building - Framing Items Corrected Troy Crews 9/2/2020
Passed: Building - Insulation Troy Crews 9/2/2020
Passed: Plumbing/Gas - 2nd Rough-In Items Corrected Troy Crews 9/2/2020
Failed: Electrical - Permanent Power Electrical Work Not Done To Release Power Matt Forsyth 10/8/2020
Rescheduled 10/9/2020:Electrical - Permanent Power Troy Crews 10/8/2020
Cancelled: Engineering - Final Driveway Waiver Permit Converted To A Culvert Permit. That Had Already Been Installed. Melissa Garber 10/8/2020
Passed: Engineering - Initial Driveway Mccormick, David 10/9/2020
Passed: Engineering - Final Driveway Mccormick, David 10/9/2020
Passed: Electrical - Temporary Service Matt Forsyth 10/9/2020
Release to power company Culvert Permit Approved 10.9.20 Matt Forsyth 10/9/2020
Passed: Electrical - Permanent Power Need Septic Released Matt Forsyth 11/18/2020
Septic Release Inspection Health Dept 11/20/2020
Release to power company Melissa Garber 11/23/2020
Failed: Building - Final Work On Home Needs To Finished Matt Forsyth 12/9/2020
Passed: Building - Final Waiting On Chad For Ground Engineering Matt Forsyth 12/11/2020
Certificate-Release Certificate County Engineer Has Approved T.c. Matt Forsyth 1/12/2021
Documents
File Name Date File Size