Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 228 SW FRITZ GLN
LAKE CITY, FL 32024
Parcel #: 02723-002
Acres: 1.18
Owner: Reiter Austin & Lindsey
Subdivision:
Zoning: RSF-2
Flood Zone: A
District: 3
Application #: 46982
Permit #: 000040555
Related Permit: Culvert Waiver: 000040554
Submitted: Thursday, August 27, 2020
Issued: Friday, September 18, 2020
Expires: Thursday, April 22, 2021
Completed: Thursday, April 22, 2021
Status: Completed
Septic Release? Yes
Notes:
LOMA 66A ON FILE FOR THIS PROPERTY
Job Details
Finished floor requirement
Fema map number 12023C0289D
Standards Culvert installation shall conform to the approved site plan standards
Requirements An 18” storm pipe of approved material is Permanent An 18” storm pipe of approved material is required with a minimum length of 32 feet. 4” Concrete Pads shall be located on each mitered end section and shall be 5’ wide by 7’ long. INVERT ELEVATION OF SIDEDRAINS ARE 2.4' LOWER THAN CENTERLINE OF ROADWAY. with a minimum length of 32 feet. 4” Concrete Pads shall be located on each mitered end section, and shall be 5’ wide by 7’ long
Status Permanent
Type of connection for access road Curb & Gutter
Type of construction of property Site Built Home
Normal vehicle usage: Automobiles
Side Drain required Yes
Side Drain Size 18
Study Required No
Estimated Number of Vehicle trips per day 4
Is the access for commercial or residential use? Residential
County Road Type Paved
Review Notes
8/6/2020 Application pending.
8/27/2020 Point Review - Printed-Online Application
8/27/2020 Point Review - Reviewed
9/14/2020 Plan Review - Documents Required
9/16/2020 Plan Review - Reviewed
9/16/2020 Zoning Review - Reviewed
9/18/2020 Permit Issued Permit #000040555 created and approved.
3/30/2021 Final Review - Payment Needed NEEDED: EH (ISSUE CULVERT WAIVER) - 09.14.20 - CHANGED STATUS AS PER BLAKE...(JW) NEED TRUSS PLANS ONLY LAYOUT IN FILE
5/3/2024 Point Review - Reviewed NEEDED: EH (ISSUE CULVERT WAIVER) - 09.14.20 - CHANGED STATUS AS PER BLAKE...(JW) NEED TRUSS PLANS ONLY LAYOUT IN FILE
Contractors
Name/ Business License Title Role
Blake Lunde Ii
Blake Construction Company Of North Florida Inc
Liability Insurance Expired.
CBC1253408 Building Contractor Contractor
Aaron Hokanson
Aaron's Plumbing Corporation
Liability Insurance Expired.
CFC1426264 Plumbing Contractor Subcontractor
Blake N Lunde Ii
Blake Roofing Inc
Liability Insurance Expired.
CCC1331699 Cert. Roofing Subcontractor
Matthew H Burns
Matt Burns Electric, Inc.
EC13006531 Electrical Contractor Subcontractor
Clinton G Wilson
Wilson Heat & Air Inc
CAC057886 Class B A/c Subcontractor
Inspections
Inspection Notes Performed By Date
Failed: Electrical - Temporary Service Panel Needs To. Be Cleaned Out And Holes Plugged Matt Forsyth 10/20/2020
Passed: Electrical - Temporary Service Matt Forsyth 10/21/2020
Release to power company Matt Forsyth 10/21/2020
Passed: Building - Footer Matt Forsyth 10/22/2020
Passed: Engineering - Setbacks Matt Forsyth 10/22/2020
Passed: Building - Footer Matt Forsyth 10/22/2020
Passed: Engineering - Setbacks Matt Forsyth 10/22/2020
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 10/30/2020
Passed: Building - Monolithic Slab House And Porch Only Matt Forsyth 11/4/2020
Passed: Building - Slab House And Porches Only Matt Forsyth 11/4/2020
Passed: Building - Monolithic Slab Carport Matt Forsyth 11/6/2020
Passed: Engineering - Setbacks Matt Forsyth 11/6/2020
Passed: Building - Roof Decking Matt Forsyth 11/17/2020
Passed: Building - Wall Sheathing Matt Forsyth 11/17/2020
Passed: Building - Framing Matt Forsyth 12/3/2020
Passed: Building - Strapping Matt Forsyth 12/3/2020
Passed: Electrical - 2nd Rough-In Matt Forsyth 12/3/2020
Passed: Mechanical - Rough In Matt Forsyth 12/3/2020
Passed: Plumbing/Gas - 2nd Rough-In Matt Forsyth 12/3/2020
Passed: Building - Insulation Walls And Vaulted Ceilings Only Matt Forsyth 12/21/2020
Passed: Electrical - Permanent Power Need Septic Release Matt Forsyth 3/31/2021
Release to power company Laurie Hodson 4/5/2021
Septic Release Inspection Health Dept 4/5/2021
Passed: Building - Final Matt Forsyth 4/22/2021
Documents
File Name Date File Size