Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 952 SW MANDIBA DR
LAKE CITY, FL 32024
Parcel #: 09280-171
Acres: 1.02
Owner: Bruce And Susan Mcnutt
Subdivision: Oaks Of Lake City Phase 2
Zoning: PRRD
Flood Zone: X
District: 5
Application #: 47865
Permit #: 000041089
Related Permit: Culvert Waiver: 000041088
Submitted: Wednesday, December 9, 2020
Issued: Thursday, December 31, 2020
Expires: Wednesday, August 4, 2021
Completed: Wednesday, August 4, 2021
Status: Completed
Septic Release? Yes
Notes:
ELEVATION CONFIRMATION LETTER REC'D @ 81.50'
Job Details
Finished floor requirement
Fema map number 12023C0190D
Type Roofing Job Other
Further Job Details (Explain if decking is being replaced and or Repairs are being done.) overlay of shingle on 1 layer of shingles
Type of structure House
Commercial or Residential Residential
Roof Area (for this job) Sq Ft 4275
No. of Stories 1
Roof Pitch 4:12 or Greater
Is the existing roof being removed? No
Type of New Roofing Product Asphalt Shingles
Florida Product Approval Number fl10124
Product Manufacturer gaf
Product Description asphalt architectural shingles
Building Code Edition 2020 Florida Building Code 7th Edition and Florida Statute 553.844
Sealed roof decking options: (Must select an option.) Other (explain)
Ventilation: Ridge Vent
Flashing: Replace with L-Flashing
Drip Edge: Replace All
Valley Treatment: Use Existing
Any cable and/or race-way wiring located on or within the roof assembly? No
Review Notes
11/30/2020 Application pending.
12/9/2020 Point Review - On Hold-Incomplete
12/10/2020 Point Review - Printed-Online Application
12/10/2020 Zoning Review - Reviewed
12/16/2020 Plan Review - Documents Required
12/21/2020 Plan Review - Documents Required
12/22/2020 Plan Review - Reviewed
12/31/2020 Zoning Review - Reviewed
12/31/2020 Final Review - Payment Needed
12/31/2020 Permit Issued Permit #000041089 created and approved.
6/28/2021 Final Review - Payment Needed CULLY: ENERGY CALCULATIONS- REC'D MANUAL "J"- REC'D EH- REC'D WIND LOAD/ENG.- REC'D
Contractors
Name/ Business License Title Role
Isaiah Cully
Ic Construction Llc
CBC1259655 Building Contractor Contractor
Everton D Ruddock
D&s Lighting Inc
EC13003800 Electrical Contractor Subcontractor
Clinton G Wilson
Wilson Heat & Air Inc
CAC057886 Class B A/c Subcontractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Tyler M Turner
Tmt Roofing Llc
CCC1330410 Cert Roofing Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Troy Crews 1/5/2021
Passed: Engineering - Setbacks Troy Crews 1/5/2021
Passed: Plumbing/Gas - 1st Underground Rough–In Troy Crews 1/19/2021
Passed: Building - Slab Troy Crews 1/20/2021
Passed: Building - Roof Decking Troy Crews 2/22/2021
Passed: Building - Wall Sheathing Troy Crews 2/22/2021
Failed: Building - Insulation Need Framing And Rough In Inspections And Elevation Confirmation Letter May Have To Remove Some Insulation. Troy Crews 4/7/2021
Passed: Building - Framing Troy Crews 4/14/2021
Passed: Electrical - 2nd Rough-In Troy Crews 4/14/2021
Failed: Mechanical - Rough In Bath Fan Duct Not Connected Call Back In Prior To Sheetrock. Troy Crews 4/14/2021
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 4/14/2021
Passed: Building - Insulation Troy Crews 4/20/2021
Passed: Mechanical - Rough In Troy Crews 4/20/2021
Septic Release Inspection Health Dept 6/4/2021
Passed: Electrical - Permanent Power Troy Crews 6/29/2021
Release to power company Troy Crews 6/29/2021
Passed: Building - Final Troy Crews 8/4/2021
Documents
File Name Date File Size