Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 809 NW MILO TER
LAKE CITY, FL 32055
Parcel #: 02032-107
Acres: 5.01
Owner: John & Elizabeth Harrison
Subdivision: Hills Of Huntsville
Zoning: A-3
Flood Zone: X
District: 3
Application #: 43830
Permit #: 000038763
Related Permit: Culvert: 000038764
Submitted: Thursday, October 17, 2019
Issued: Thursday, October 17, 2019
Expires: Friday, June 26, 2020
Completed: Friday, June 26, 2020
Status: Completed
Septic Release? Yes
Notes:
MFE @ 99.50, NEED ELEVATION LETTER BEFORE NAILING, ELEVATION LETTER REC'D AT 101.08'
Job Details
Finished floor requirement
Fema map number 12023C0280D
This is the construction of a Single Family Dwelling
Setbacks Front 30
Setback Side 1 25
Setback Side 2 25
Setbacks Rear 25
Stories 1
Heated Area (Sqft) 2628
Total Area (Sqft) 3721
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000) 19-0652
Review Notes
10/17/2019 Permit Issued Permit # created and approved.
Contractors
Name/ Business License Title Role
Sara E Gresham
John Norris Construction, Llc
CRC1331978 Cert. Residential Contractor
Donald R Hollingsworth
Holly Electric, Inc.
EC13005429 Electrical Subcontractor
Jan R Touchton
Touchton's Heat & Air
CAC058747 Cert. A/c Class “a” Subcontractor
Don C Bills Sr
Hometown Plumbing Services Llc
CFC1428890 Plumbing Contractor Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway Mccormick, David 10/21/2019
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 11/5/2019
Passed: Building - Monolithic Slab Matt Forsyth 11/13/2019
Passed: Engineering - Setbacks Matt Forsyth 11/13/2019
Passed: Electrical - Temporary Service Tommy Matthews 12/2/2019
Release to power company Tommy Matthews 12/2/2019
Building- 12/27/2019
Passed: Building - Roof Decking Matt Forsyth 12/27/2019
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 12/27/2019
Passed: Building - Framing Matt Forsyth 1/10/2020
Passed: Mechanical - Above Ceiling Matt Forsyth 1/10/2020
Passed: Plumbing/Gas - 2nd Rough-In Matt Forsyth 1/10/2020
Passed: Electrical - 2nd Rough-In Matt Forsyth 1/16/2020
Passed: Building - Insulation Spray Foam Walls And Ceiling Matt Forsyth 1/23/2020
Septic Release Inspection Need Driveway Approval Health Dept 4/28/2020
Passed: Electrical - Permanent Power Need Driveway Release To Release Power Matt Forsyth 4/29/2020
Release to power company Melissa Garber 6/1/2020
Passed: Engineering - Final Driveway Mccormick, David 6/1/2020
Passed: Building - Final Release Of Co Pending Blower Door Test And Letter From Ac Contractor Troy Crews 6/25/2020
Certificate-Release Certificate Troy Crews 6/26/2020