Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 458 SW PINEHURST DR
LAKE CITY, FL 32024
Parcel #: 03087-122
Acres: 0.73
Owner: Shane Thomson
Subdivision: Forest Country Sixth Addition
Zoning: RSF-2
Flood Zone: X
District: 3
Application #: 47778
Permit #: 000040971
Related Permit: Culvert: 000040972
Submitted: Monday, November 16, 2020
Issued: Friday, January 15, 2021
Expires: Monday, September 20, 2021
Completed: Monday, September 20, 2021
Status: Completed
Septic Release? Yes
Notes:
ELEVATION LETTER RECIEVED STATING FINISHED FLOOR ELEVATION OF SLAB SHALL BE 104.2'. NEED SURVEYOR ELEVATION CONFIRMATION LETTER BEFORE NAILING INSPECTION. SURVEYOR CONFIRMATION LETTER REC'D AT 105.2'
Job Details
Finished floor requirement
Fema map number 12023C0290D
Type Roofing Job Replacement - Tear off Existing and Replace
Further Job Details (Explain if decking is being replaced and or Repairs are being done.) Decking will be replaced if rotten wood is found
Type of structure House
Commercial or Residential Residential
Roof Area (for this job) Sq Ft 31
No. of Stories 1
Roof Pitch 2:12 to 4:12
Is the existing roof being removed? Yes
Type of New Roofing Product Asphalt Shingles
Florida Product Approval Number Fl10124
Product Manufacturer GAF
Product Description Timberline
Building Code Edition 2020 Florida Building Code 7th Edition and Florida Statute 553.844
Sealed roof decking options: (Must select an option.) two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Ventilation: Ridge Vent
Flashing: Use Existing
Drip Edge: Replace All
Valley Treatment: New Mineral Surface
Second Roof Pitch (if applicable) 4:12 or Greater
Any cable and/or race-way wiring located on or within the roof assembly? No
Review Notes
11/16/2020 Application pending.
11/16/2020 Point Review - Printed-Online Application
11/25/2020 Plan Review - Reviewed
11/25/2020 Plan Review - Documents Required
11/25/2020 Plan Review - Reviewed
12/1/2020 Zoning Review - Reviewed
12/4/2020 Permit Issued Permit #000040971 created and approved.
1/15/2021 Permit reissued to reflect updated information.
7/15/2021 Final Review - Payment Needed NEEDED: JW SPOKE W/SUZANNE 11.16.20 RESIDENTIAL CHECKLIST - REC'D 11.18.20
Contractors
Name/ Business License Title Role
Bryan Zecher
Bryan Zecher Construction Inc
CBC054575 Cert.building Contractor Contractor
Marcus Matthews
Matthews Electric Llc
EC13005459 Electrical Contractor Subcontractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Anthony R Franks
Franks & Lane Heating And Air Llc
CAC1818631 Cert. A/c Class “b” Subcontractor
Robert Ogles Ii
Ogles Roofing & Construction Llc
CCC1328699 Cert Roofing Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Matt Forsyth 12/29/2020
Passed: Engineering - Setbacks Troy Crews 12/29/2020
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 1/26/2021
Passed: Building - Slab Matt Forsyth 2/12/2021
Passed: Building - Framing Matt Forsyth 3/18/2021
Passed: Electrical - 2nd Rough-In Troy Crews 4/13/2021
Passed: Mechanical - Rough In Troy Crews 4/13/2021
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 4/13/2021
Cancelled: Electrical - Temporary Service Melissa Garber 4/19/2021
Passed: Electrical - Temporary Service Matt Forsyth 4/22/2021
Release to power company Matt Forsyth 4/22/2021
Passed: Building - Insulation Troy Crews 6/1/2021
Passed: Electrical - Permanent Power Need Septic And Driveway Releases Matt Forsyth 7/16/2021
Septic Release Inspection Health Dept 8/10/2021
Release to power company Melissa Garber 8/11/2021
Passed: Engineering - Final Driveway Mccormick, David 8/11/2021
Passed: Building - Final Matt Forsyth 9/20/2021
Documents
File Name Date File Size