Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 290 SW FIELDSTONE COURT
LAKE CITY, FL 32024
Parcel #: 02438-161
Acres: 0.51
Owner: Mf Butler Homes Llc
Subdivision: Emerald Cove
Zoning: RSF-2
Flood Zone: X
District: 3
Application #: 40078
Permit #: 000037593
Related Permit: Culvert: 000002724
Submitted: Friday, January 4, 2019
Issued: Friday, January 4, 2019
Expires: Monday, November 11, 2019
Completed:
Status:
Septic Release? Yes
Notes:
FLOOR ONE FOOT ABOVE THE ROAD, NOC ON FILE ENGINEER LETTER REC'D FOR MINIMUM FLOOR ELEVATION TO BE 12" ABOVE THE EXISTING GROUND AT ANY POINT ALONG THE PERIMETER AND THE GROUND GRADED TO CONVEY STORMWATER RUNOFF AWAY FROM THE STRUCTURE. ELEVATION LETTER REC'D @ 1.01' ABOVE THE HIGHEST ADJACENT GRADE
Job Details
Finished floor requirement
Fema map number 12023C0170D
Type Roofing Job Overlay with Metal
Type of structure House
Commercial or Residential Commercial
Roof Area (for this job) Sq Ft 2177
No. of Stories 1
Roof Pitch 2:12 to 4:12
Is the existing roof being removed? No
Explain if not removing the existing roofing material? Metal Roof-over
Type of New Roofing Product Metal
Florida Product Approval Number 4595.17
Product Manufacturer Tri-County Metals
Product Description Ultra Rib over 1x4 purlins over plywood/shingles
Building Code Edition 2020 Florida Building Code 7th Edition and Florida Statute 553.844
Sealed roof decking options: (Must select an option.) Other (explain)
Sealed roof decking explanation for other option. Metal roof-over
Ventilation: Ridge Vent
Flashing: Replace All
Drip Edge: Replace All
Valley Treatment: New Metal
Any cable and/or race-way wiring located on or within the roof assembly? No
Review Notes
Contractors
Name/ Business License Title Role
Mark Bauer

CBC1259633
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway David Mccormick 1/7/2019
Passed: Building - Footer Troy Crews 1/9/2019
Passed: Engineering - Setbacks Troy Crews 1/9/2019
Passed: Electrical - Temporary Service Troy Crews 1/24/2019
Release to power company Troy Crews 1/24/2019
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 2/1/2019
Passed: Building - Slab Troy Crews 2/6/2019
Rescheduled 2/22/2019:Building - Roof Decking Troy Crews 2/21/2019
Rescheduled 2/22/2019:Building - Ext Strapping/Wall Sheathing Troy Crews 2/21/2019
Passed: Building - Roof Decking Troy Crews 2/22/2019
Passed: Building - Ext Strapping/Wall Sheathing Troy Crews 2/22/2019
Passed: Electrical - Rough In Troy Crews 3/6/2019
Passed: Mechanical - Rough In Troy Crews 3/6/2019
Passed: Plumbing/Gas - Rough In Troy Crews 3/6/2019
Failed: Building - Framing Check Back Two Gang Window Sections Calls For 3 Jack Studs, May Need To Consult Engineer, Also Nee N.o.c. Asap, Call Back In With Insulation. Troy Crews 3/6/2019
Passed: Building - Insulation Troy Crews 3/8/2019
Passed: Building - Framing Pending Clarification From Engineer On Jack Studs Under Windows West Walll Troy Crews 3/8/2019
Passed: Electrical - Permanent Power Need Eh & Final driveway Tommy Matthews 4/25/2019
Passed: Engineering - Final Driveway David Mccormick 4/29/2019
Release to power company Rec'd Eh 04.30.19 Tm 4/30/2019
Septic Release Inspection Health Dept 5/1/2019
Passed: Building - Final Need Blower Door Test Tommy Matthews 5/15/2019
Documents
File Name Date File Size