| Application #: | 47892 |
| Permit #: |
000041056 |
| Related Permit: |
|
| Submitted: | Monday, December 7, 2020 |
| Issued: | Tuesday, December 22, 2020 |
| Expires: | Tuesday, February 23, 2021 |
| Completed: | Tuesday, February 23, 2021 |
| Status: |
Completed |
| Septic Release? |
Yes |
Job Details
| Finished floor requirement |
Meet existing structure |
| Fema map number |
12023C0395C |
| In floodway |
N |
| Description of addition: |
closet addition |
| Select driveway access to property: |
Existing Drive |
| Fire sprinklers? |
No |
| Setbacks Front |
30 |
| Setback Side 1 |
25 |
| Setback Side 2 |
25 |
| Setback Rear |
25 |
| Stories |
1 |
| Heated Area (Sqft) |
160.2 |
| Total Area (Sqft) |
160.2 |
| Total Estimated Cost |
22975.00 |
| Building Height |
15 |
| Building Code Construction Type |
V |
| Building Code Element |
B |
| Building Code Occupancy Types |
Residential |
| Occupancy Use Title |
single family |
| Dev Permit # |
F023- |
| Building Code Edition |
Florida Building Code 2017 6th Edition & 2014 National Electrical Code |
| Septic# |
20-0973 |
| Is this an addition for commercial or residential use? |
Residential |
Review Notes
| 12/3/2020 |
Application pending. |
| 12/7/2020 |
Point Review - Printed-Online Application |
| 12/8/2020 |
Zoning Review - Reviewed |
| 12/10/2020 |
Plan Review - Documents Required |
| 12/21/2020 |
Plan Review - Documents Required |
| 12/21/2020 |
Plan Review - Reviewed |
| 12/21/2020 |
Final Review - Payment Needed |
| 12/22/2020 |
Permit Issued |
Contractors
| Name / Business |
License |
Title |
Role |
Bryan Zecher Bryan Zecher Construction Inc
|
CBC054575 |
Cert.building Contractor |
Contractor |
Marcus Matthews Matthews Electric Llc
|
EC13005459 |
Electrical Contractor |
Subcontractor |
Anthony R Franks Franks & Lane Heating And Air Llc
|
CAC1818631 |
Cert. A/c Class “b” |
Subcontractor |
Cody Barrs Barrs Plumbing Inc
|
CFC1427145 |
Plumbing Contractor |
Subcontractor |
Robert Ogles Ii Ogles Roofing & Construction Llc
|
CCC1328699 |
Cert Roofing |
Subcontractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Septic Release Inspection |
|
Health Dept |
12/21/2020 |
| Passed: Building - Footer |
|
Troy Crews |
1/5/2021 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
1/5/2021 |
| Passed: Building - Slab |
|
Troy Crews |
1/20/2021 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
2/4/2021 |
| Passed: Building - Framing |
|
Troy Crews |
2/4/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
2/4/2021 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
2/4/2021 |
| Passed: Building - Insulation |
|
Troy Crews |
2/9/2021 |
| Passed: Building - Final |
|
Troy Crews |
2/23/2021 |