Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 169 SW DOVE WAY
LAKE CITY, FL 32024
Parcel #: 03623-010
Acres: 3.64
Owner: Marilyn Massey
Subdivision: Hi-dri Acres
Zoning: A-3
Flood Zone: X
District: 2
Application #: 42366
Permit #: 000038451
Related Permit: Culvert Waiver: 000002862
Submitted: Thursday, August 8, 2019
Issued: Thursday, August 8, 2019
Expires: Tuesday, December 31, 2019
Completed: Tuesday, December 31, 2019
Status: Completed
Septic Release? Yes
Notes:
FLOOR ONE FOOT ABOVE THE ROAD. NOC ON FILE. SFD BUILT ON LOT 8.
Job Details
Finished floor requirement
Fema map number 12023C0380C
This is the construction of a: Classroom building
Driveway access to property: Existing Drive
Is there a Fire Sprinkler System? Yes
Setbacks Front 25'
Setback Side 1 10'
Setback Side 2 10'
Setback Rear 15'
Describe commercial use: Classroom building
Stories 1
Heated Area (Sqft) 6500
Total Area (Sqft) 6500
Building Height 15
Building Code Construction Type III
Building Code Element B
Building Code Occupancy Types Education
Occupancy Use Title classrooms
Dev Permit # F023-
Design Occupant Load 104
Building Code Edition 2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000) 24-0250
Sealed roof decking options. (Must select one.) two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps 200
Review Notes
Contractors
Name/ Business License Title Role
Mark Bauer

CBC1259633
Inspections
Inspection Notes Performed By Date
Passed: Electrical - Temporary Service Tommy Matthews 8/13/2019
Release to power company Tommy Matthews 8/13/2019
Failed: Plumbing/Gas - Underground Rough-In On All Exterior Footings Water Supply Pipe Needs To Be Sleeved And Also Needs To Be Staked To Prevent Movement During Placement Of Concrete Matt Forsyth 8/22/2019
Passed: Building - Slab Troy Crews 8/26/2019
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 8/26/2019
Passed: Building - Roof Decking Matt Forsyth 9/16/2019
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 9/16/2019
Passed: Building - Framing Matt Forsyth 10/1/2019
Passed: Electrical - 2nd Rough-In Matt Forsyth 10/1/2019
Passed: Mechanical - Above Ceiling Matt Forsyth 10/1/2019
Passed: Plumbing/Gas - 2nd Rough-In Matt Forsyth 10/1/2019
Passed: Building - Insulation Tommy Matthews 10/7/2019
Septic Release Inspection Health Dept 11/5/2019
Passed: Electrical - Permanent Power Matt Forsyth 11/15/2019
Release to power company Matt Forsyth 11/15/2019
Passed: Building - Final Matt Forsyth 12/31/2019
Release to power company Matt Forsyth 12/31/2019
Documents
File Name Date File Size