Inspection |
Notes |
Performed By |
Date |
Foundation Inspection |
|
Tommy Matthews |
10/25/2017 |
Setback Inspection |
|
Tommy Matthews |
10/25/2017 |
Failed: Building - Slab |
No Plans On Site. Need Toilet |
Tommy Matthews |
12/5/2017 |
Slab Inspection |
|
Troy Crews |
12/7/2017 |
Passed: Building - Slab |
|
Troy Crews |
12/7/2017 |
Passed: Building - Roof-In Progress |
|
Troy Crews |
1/17/2018 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
1/17/2018 |
Rescheduled 1/29/2018:Building - Framing |
|
Troy Crews |
1/26/2018 |
Rescheduled 1/29/2018:Electrical - Rough In |
|
Troy Crews |
1/26/2018 |
Rescheduled 1/29/2018:Mechanical - Rough In |
|
Troy Crews |
1/26/2018 |
Rescheduled 1/29/2018:Plumbing/Gas - Rough In |
|
Troy Crews |
1/26/2018 |
Failed: Mechanical - Rough In |
Not Complete |
Troy Crews |
1/29/2018 |
Failed: Plumbing/Gas - Rough In |
Not Complete No Pressure |
Troy Crews |
1/29/2018 |
Passed: Building - Framing |
|
Troy Crews |
1/29/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
1/29/2018 |
Failed: Mechanical - Rough In |
Not Complete |
Troy Crews |
1/29/2018 |
Failed: Plumbing/Gas - Rough In |
Not Complete No Pressure |
Troy Crews |
1/29/2018 |
Passed: Mechanical - Rough In |
|
Troy Crews |
1/31/2018 |
Passed: Plumbing/Gas - Rough In |
|
Troy Crews |
1/31/2018 |
Passed: Building - Insulation |
|
Troy Crews |
3/1/2018 |
Release to power company |
|
Troy Crews |
8/13/2018 |
Passed: Electrical - Permanent Power |
Permit Expired 2/10/19 Before Final Inspection Was Done. Renewed Permit On 4/30/19. |
Troy Crews |
8/14/2018 |
Failed: Building - Final |
Upstairs Bath Check Gfci, Need Handrail On Upper Stair, Need Final Termite Certificate |
Troy Crews |
5/1/2019 |
Passed: Building - Final |
Items Corrected |
Troy Crews |
5/22/2019 |