Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

Storage Building Permit

Address 620 SW MAULDIN AVE
LAKE CITY, FL 32024
Parcel #: 03265-108
Acres: 5.00
Owner: Pritchard John L, Pritchard Heather
Subdivision: Mauldin Woodlands Phase 1
Zoning: A-3
Flood Zone: X
District: 2
Application #: 66941
Permit #: 000051445
Related Permit: Right-of-Way Access/Driveway: 000050995
Submitted: Thursday, September 5, 2024
Issued: Monday, September 22, 2025
Expires: Tuesday, June 2, 2026
Completed:
Status: Permit Reissued
Septic Release? Yes
Notes:
OPEN ACCESSORY STRUCTURE.
Job Details
Finished floor requirement
Fema map number 12023C0195D
Special temporary use permit number: FPL
Septic # (00-0000) or (X00-000) 06-0745-N
Setbacks Front 30.00
Setback Side 1 25.00
Setbacks Rear 25.00
Review Notes
9/5/2024 Point Review - Processing
9/6/2024 Point Review - On Hold-Incomplete
9/25/2024 Point Review - Printed-Online Application
10/2/2024 Zoning Review - Reviewed
10/4/2024 Plan Review - Reviewed
10/16/2024 Final Review - Documents Required
10/24/2024 Final Review - Documents Required
10/31/2024 Final Review - Documents Required
10/31/2024 Final Review - Documents Required
11/4/2024 Final Review - Documents Required
11/7/2024 Final Review - Reviewed
11/7/2024 Final Review - Payment Needed
11/8/2024 Permit Issued
9/22/2025 Permit Reissued
Contractors
Name/ Business License Title Role
Inspections
Inspection Notes Performed By Date
Septic Release Inspection Health Dept 11/5/2024
Passed: Building - Footer Gary Pitzer 2/10/2025
Passed: Engineering - Setbacks Gary Pitzer 2/10/2025
Passed: Building - Spot Check Your Project Is Beyond Your Scope Of Work On Yor Permit. Your Permit Is For A Open Storage Building,. Please Contact Our Office About Build Out Permit, Work In Progress At Site Gary Pitzer 9/23/2025
Passed: Building - Framing Troy Crews 12/4/2025
Passed: Electrical - 2nd Rough-In Troy Crews 12/4/2025
Passed: Mechanical - Rough In Troy Crews 12/4/2025
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 12/4/2025