Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

Demolition Permit

Address 694 SE COUNTY ROAD 245
LAKE CITY, FL 32025
Parcel #: 07581-000
Acres: 20.47
Owner: Abp Fl (lake City) Llc
Subdivision:
Zoning: I
Flood Zone: X
District: 4
Application #: 65427
Permit #: 000050344
Related Permit:
Submitted: Friday, May 24, 2024
Issued: Friday, July 12, 2024
Expires: Friday, July 26, 2024
Completed: Friday, July 26, 2024
Status: Completed
Septic Release? No
Notes:
CALL FOR LOCATES PRIOR TO DEMOLITION
LAKE CITY UTLITY CUSTOMER SERVICE NOTES Locates must be obtained to ensure that the existing utility infrastructure is not damaged or obstructed.
Job Details
Finished floor requirement
Fema map number 12023C0311D
This is a demolition of: (Please explain) Removal & disposal of (1) 10K UST
Residential, Commercial or Storage Tank Storage Tank
Is there an existing septic tank on the property? No
Building Code Edition 2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Review Notes
5/17/2024 Application pending.
5/24/2024 Application submitted by applicant.
5/24/2024 City of Lake City Utilities Notified.
5/29/2024 Final Review - On Hold-Incomplete
5/29/2024 Point Review - Printed-Online Application
5/30/2024 Final Review - On Hold-Incomplete
6/3/2024 Zoning Review - Reviewed
6/3/2024 Plan Review - Reviewed
6/3/2024 Final Review - Documents Required
6/4/2024 Final Review - Documents Required
6/5/2024 Final Review - Documents Required
6/10/2024 Final Review - Documents Required
6/17/2024 Final Review - Documents Required
6/25/2024 Final Review - Documents Required
7/2/2024 Final Review - Documents Required
7/9/2024 Final Review - Documents Required
7/9/2024 Final Review - Reviewed
7/9/2024 Final Review - Payment Needed
7/12/2024 Permit Issued
Contractors
Name/ Business License Title Role
Steven Nale
The Oscar W Larson Company
CBC1266468 Cert. Building Contractor
Inspections
Inspection Notes Performed By Date
Cancelled: Demolition - Demolition Final Troy Crews 7/24/2024
Failed: Demolition - Tank Removal Final Tank Out Backfill Not Complete In Progress Troy Crews 7/24/2024
Passed: Demolition - Demolition Final Troy Crews 7/26/2024
Passed: Demolition - Tank Removal Final Troy Crews 7/26/2024