Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
7/20/2020 |
Cancelled: Engineering - Final Driveway |
|
Melissa Garber |
8/14/2020 |
Passed: Building - Footer |
|
Troy Crews |
8/17/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
8/17/2020 |
Failed: Building - Footer |
Not Ready |
Troy Crews |
8/28/2020 |
Failed: Engineering - Setbacks |
|
Troy Crews |
8/28/2020 |
Passed: Building - Footer |
Porches |
Troy Crews |
9/4/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
9/4/2020 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
9/17/2020 |
Release to power company |
|
Troy Crews |
9/17/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
10/2/2020 |
Passed: Building - Slab |
|
Troy Crews |
10/8/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Radiant Heat Under Floor Tubing |
Matt Forsyth |
10/13/2020 |
Passed: Building - Roof Decking |
Partial Front Half |
Troy Crews |
12/8/2020 |
Passed: Building - Roof Decking |
|
Troy Crews |
12/15/2020 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
12/21/2020 |
Passed: Building - Framing |
|
Troy Crews |
2/9/2021 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
2/9/2021 |
Passed: Mechanical - Rough In |
|
Troy Crews |
2/9/2021 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
No Pressure On Water Lines |
Troy Crews |
2/9/2021 |
Passed: Building - Insulation |
|
Troy Crews |
2/15/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
2/15/2021 |
Septic Release Inspection |
|
Health Dept |
6/4/2021 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
6/10/2021 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
6/11/2021 |
Release to power company |
|
Troy Crews |
6/11/2021 |
Passed: Building - Final |
Need To Pour Pad For Back Step, Also Clean Up Wiring For Radiant Floor Pump Send Pictures For Release. |
Troy Crews |
7/27/2021 |
Certificate-Release Certificate |
Pictures Sent On 2 Items |
Troy Crews |
7/30/2021 |