Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 215 SW COLONY GLEN
LAKE CITY, FL 32024
Parcel #: 03761-143
Acres: 5.00
Owner: Wayne & Wanda Clemons/bobbie Pizzagalli
Subdivision: Meadowlands
Zoning: A-3
Flood Zone: X
District: 4
Application #: 42325
Permit #: 000038428
Related Permit: Culvert: 000002852
Submitted: Thursday, August 1, 2019
Issued: Thursday, August 1, 2019
Expires: Thursday, May 21, 2020
Completed: Thursday, May 21, 2020
Status: Completed
Septic Release? Yes
Notes:
NOC ON FILE, PER PLAT MINIMUM FLOOR ELEVATION IS 82', NEED ELEVATION CONFRMATION LETTER AT SLAB, FLOOR ELEVATION LETTER REC'D AT 82.00'
Job Details
This is the construction of a SFD/UTILITY
Heated Area (Sqft) 2069.00
Total Area (Sqft) 3060.00
Stories 1
Setbacks Front 30.00
Setback Side 1 25.00
Setback Side 2 25.00
Setbacks Rear 25.00
Septic# (00-0000) or (X00-000) 19-0519
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Fema map number 12023C0485C
Review Notes
Contractors
Name/ Business License Title Role
Wayne Clemons

OWNER
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway Mccormick, David 8/2/2019
Passed: Electrical - Temporary Service Troy Crews 8/2/2019
Release to power company Troy Crews 8/2/2019
Passed: Building - Footer Tommy Matthews 8/7/2019
Passed: Engineering - Setbacks Tommy Matthews 8/7/2019
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 8/27/2019
Passed: Building - Slab Troy Crews 9/6/2019
Passed: Building - Lintel/Tie Beam Troy Crews 9/23/2019
Passed: Building - Masonry Wall Reinforcing Troy Crews 9/23/2019
Passed: Building - Vertical Cells/Columns Troy Crews 9/23/2019
Passed: Building - Roof Decking Troy Crews 10/16/2019
Passed: Building - Framing Troy Crews 10/21/2019
Passed: Building - Ext Strapping/Wall Sheathing Roof Sheathing Tommy Matthews 11/13/2019
Failed: Electrical - 2nd Rough-In Need Cable Staples Within 6 Inches Of Electrical Box Matt Forsyth 11/14/2019
Passed: Mechanical - Above Ceiling Matt Forsyth 11/14/2019
Passed: Mechanical - Rough In Matt Forsyth 11/14/2019
Passed: Plumbing/Gas - 2nd Rough-In Matt Forsyth 11/14/2019
Passed: Building - Insulation Troy Crews 12/2/2019
Passed: Electrical - 2nd Rough-In Wires Stapled Near Boxes Troy Crews 12/2/2019
Passed: Building - Lath/Stucco Troy Crews 12/5/2019
Septic Release Inspection Health Dept 12/16/2019
Passed: Engineering - Final Driveway Mccormick, David 3/2/2020
Passed: Electrical - Permanent Power Troy Crews 3/3/2020
Release to power company Troy Crews 3/3/2020
Passed: Building - Final Owner To Have Final Perimeter Termite Spray Done Troy Crews 5/21/2020