Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
8/2/2019 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
8/2/2019 |
Release to power company |
|
Troy Crews |
8/2/2019 |
Passed: Building - Footer |
|
Tommy Matthews |
8/7/2019 |
Passed: Engineering - Setbacks |
|
Tommy Matthews |
8/7/2019 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Troy Crews |
8/27/2019 |
Passed: Building - Slab |
|
Troy Crews |
9/6/2019 |
Passed: Building - Lintel/Tie Beam |
|
Troy Crews |
9/23/2019 |
Passed: Building - Masonry Wall Reinforcing |
|
Troy Crews |
9/23/2019 |
Passed: Building - Vertical Cells/Columns |
|
Troy Crews |
9/23/2019 |
Passed: Building - Roof Decking |
|
Troy Crews |
10/16/2019 |
Passed: Building - Framing |
|
Troy Crews |
10/21/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
Roof Sheathing |
Tommy Matthews |
11/13/2019 |
Failed: Electrical - 2nd Rough-In |
Need Cable Staples Within 6 Inches Of Electrical Box |
Matt Forsyth |
11/14/2019 |
Passed: Mechanical - Above Ceiling |
|
Matt Forsyth |
11/14/2019 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
11/14/2019 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
11/14/2019 |
Passed: Building - Insulation |
|
Troy Crews |
12/2/2019 |
Passed: Electrical - 2nd Rough-In |
Wires Stapled Near Boxes |
Troy Crews |
12/2/2019 |
Passed: Building - Lath/Stucco |
|
Troy Crews |
12/5/2019 |
Septic Release Inspection |
|
Health Dept |
12/16/2019 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
3/2/2020 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
3/3/2020 |
Release to power company |
|
Troy Crews |
3/3/2020 |
Passed: Building - Final |
Owner To Have Final Perimeter Termite Spray Done |
Troy Crews |
5/21/2020 |