Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 166 SE LINDALE GLN
LAKE CITY, FL 32025
Parcel #: 07486-120
Acres: 1.38
Owner: Cornerstone Developments Ii, Llc
Subdivision: Haight-ashbury
Zoning: RSF-2
Flood Zone: X
District: 4
Application #: 40870
Permit #: 000038121
Related Permit: Culvert: 000002813
Submitted: Thursday, May 16, 2019
Issued: Thursday, May 16, 2019
Expires: Thursday, February 27, 2020
Completed: Thursday, February 27, 2020
Status: Completed
Septic Release? Yes
Notes:
NOC ON FILE. 1 FOOT ABOVE ROAD.
Job Details
This is the construction of a SFD/UTILITY
Heated Area (Sqft) 1500.00
Total Area (Sqft) 1974.00
Stories 1
Setbacks Front 25.00
Setback Side 1 10.00
Setback Side 2 10.00
Setbacks Rear 15.00
Septic# 19-0361
Power Company FPL
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Fema map number 12023C0311D
Review Notes
Contractors
Name/ Business License Title Role
Jerry Castagna

County License & State License & Liability Insurance & Workers Comp Expired.
CBC047842
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway David Mccormick 5/17/2019
Passed: Plumbing/Gas - Underground Rough-In Matt Forsyth 5/21/2019
Passed: Building - Slab Matt Forsyth 5/28/2019
Passed: Electrical - Temporary Service Matt Forsyth 7/25/2019
Release to power company Matt Forsyth 7/25/2019
Release to power company Resent As Per The Request Of Agent. fpl Said They Didn't Receive On 7.25.19 Mf 8/6/2019
Passed: Building - Roof Decking Matt Forsyth 8/22/2019
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 8/22/2019
Passed: Building - Framing Matt Forsyth 9/4/2019
Passed: Electrical - Rough In Matt Forsyth 9/4/2019
Passed: Mechanical - Rough In Matt Forsyth 9/4/2019
Passed: Plumbing/Gas - Tub Set/Shower Pan Matt Forsyth 9/4/2019
Passed: Plumbing/Gas - Rough In Matt Forsyth 9/4/2019
Passed: Building - Insulation Matt Forsyth 9/6/2019
Septic Release Inspection Health Dept 10/4/2019
Passed: Electrical - Permanent Power Need Driveway Final To Complete For Permanent Power Matt Forsyth 10/4/2019
Passed: Engineering - Final Driveway Mccormick, David 10/10/2019
Passed: Building - Insulation Matt Forsyth 10/10/2019
Release to power company Lh 10/11/2019
Passed: Building - Final Matt Forsyth 2/19/2020
Certificate-Release Certificate Matt Forsyth 2/27/2020