Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
Check South Property Line To Confirm 10 Ft Setback |
Troy Crews |
3/26/2019 |
Passed: Engineering - Setbacks |
|
Troy Crews |
3/26/2019 |
Passed: Plumbing/Gas - Rough In |
|
Troy Crews |
4/9/2019 |
Passed: Building - Slab |
|
Troy Crews |
4/22/2019 |
Passed: Building - Roof Decking |
|
Troy Crews |
5/20/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
5/21/2019 |
Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
6/5/2019 |
Failed: Building - Framing |
Need Plans Onsite, Check Uplift Truss T-11, Remove Timber Screws From Trusses Use Proper Simpson Screws. Will Need Reinspection Prior To Insulation |
Troy Crews |
6/5/2019 |
Failed: Electrical - Rough In |
Island Power Not Roughed In |
Troy Crews |
6/5/2019 |
Failed: Mechanical - Rough In |
Bath Fan Ducts Not Attatched |
Troy Crews |
6/5/2019 |
Failed: Plumbing/Gas - Rough In |
Need More Pressure Water Lines, Also Strap Gas Line Properly |
Troy Crews |
6/5/2019 |
Passed: Mechanical - Rough In |
|
Troy Crews |
6/11/2019 |
Passed: Plumbing/Gas - Rough In |
|
Troy Crews |
6/11/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
6/11/2019 |
Failed: Electrical - Rough In |
Island Power Not Roughed In |
Troy Crews |
6/11/2019 |
Passed: Building - Insulation |
|
Troy Crews |
6/21/2019 |
Passed: Electrical - Rough In |
|
Troy Crews |
6/21/2019 |
Passed: Building - Framing |
Screws Changed Out |
Troy Crews |
7/8/2019 |
Cancelled: Building - Framing |
|
Troy Crews |
8/7/2019 |
Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
8/7/2019 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
10/21/2019 |
Release to power company |
|
Troy Crews |
10/21/2019 |
Passed: Building - Final |
Release Pending Blower Door Test, Rec'd 11/12/19 |
Troy Crews |
11/7/2019 |