Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 668 SW CHESTERFIELD CR
LAKE CITY, FL 32024
Parcel #: 03117-140
Acres: 0.50
Owner: Daniel & Janet Crapps
Subdivision: Crosswinds
Zoning: RSF-2
Flood Zone: X
District:
Application #: 40306
Permit #: 000037746
Related Permit: Culvert: 000002748
Submitted: Thursday, February 14, 2019
Issued: Thursday, February 14, 2019
Expires: Tuesday, August 27, 2019
Completed: Tuesday, August 27, 2019
Status: Completed
Septic Release? Yes
Notes:
1 FOOT ABOVE ROAD. NOC ON FILE. ELEVATION LETTER STATES MINIMUM FLOOR ELEVATION OF 4 INCHES ABOVE THE CROWN OF THE ADJACENT ROADWAY. CONFIRMED 6 INCHES ABOVE CROWN OF ROAD.
Job Details
This is the construction of a SFD/UTILITY
Heated Area (Sqft) 1646.00
Total Area (Sqft) 2535.00
Stories 1
Setbacks Front 25.00
Setback Side 1 10.00
Setback Side 2 10.00
Setbacks Rear 15.00
Septic# 18-0948
Power Company CLAY
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Review Notes
Contractors
Name/ Business License Title Role
James M. Lipscomb

County License & State License & Liability Insurance & Workers Comp Expired.
CBC1253543
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway David Mccormick 2/15/2019
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 3/11/2019
Failed: Building - Slab Verify One Foot Above Road Tommy Matthews 3/15/2019
Passed: Building - Monolithic Slab Troy Crews 3/18/2019
Passed: Engineering - Setbacks Troy Crews 3/18/2019
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 5/28/2019
Failed: Building - Framing Need Truss Engineering Completed Matt Forsyth 5/28/2019
Passed: Building - Framing Matt Forsyth 6/4/2019
Passed: Electrical - Rough In Matt Forsyth 6/4/2019
Passed: Mechanical - Rough In Matt Forsyth 6/4/2019
Passed: Plumbing/Gas - Rough In Matt Forsyth 6/4/2019
Rescheduled 6/11/2019:Building - Insulation Matt Forsyth 6/10/2019
Passed: Building - Insulation Matt Forsyth 6/11/2019
Passed: Electrical - Permanent Power Corrected Type Of Inspection Tommy Matthews 8/13/2019
Passed: Engineering - Final Driveway Mccormick, David 8/15/2019
Septic Release Inspection Health Dept 8/15/2019
Release to power company Tommy Matthews 8/15/2019
Passed: Building - Final Troy Crews 8/27/2019