Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 1859 SW LITTLE RD
LAKE CITY, FL 32024
Parcel #: 03387-000
Acres: 4.10
Owner: Donald & Tawnya Little
Subdivision:
Zoning: A-3
Flood Zone: X
District: 5
Application #: 39905
Permit #: 000037477
Related Permit: Culvert Waiver: 000002703
Submitted: Tuesday, November 27, 2018
Issued: Friday, December 18, 2020
Expires: Tuesday, December 29, 2020
Completed: Tuesday, December 29, 2020
Status: Completed
Septic Release? Yes
Notes:
FLOOR ONE FOOT ABOVE THE ROAD, NOC ON FILE LEGAL LOT OF RECORD PER ZONING LETTER
Job Details
Finished floor requirement
Fema map number 12023C0383D
This is the construction of a SFD, UTILITY
Setbacks Front 30.00
Setback Side 1 25.00
Setback Side 2 25.00
Setbacks Rear 25.00
Stories 1
Heated Area (Sqft) 4558.00
Total Area (Sqft) 7508.00
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000) 18-0529
Review Notes
12/18/2020 Permit Renewed
Contractors
Name/ Business License Title Role
Donald Little

County License & State License Expired.
CBC1260286
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Tommy Matthews 12/18/2018
Passed: Engineering - Setbacks Tommy Matthews 12/18/2018
Passed: Plumbing/Gas - Underground Rough-In Tommy Matthews 1/10/2019
Passed: Building - Slab Troy Crews 1/17/2019
Passed: Building - Footer Tommy Matthews 1/29/2019
Passed: Engineering - Setbacks Tommy Matthews 1/29/2019
Passed: Building - Monolithic Slab Tommy Matthews 1/29/2019
Passed: Engineering - Setbacks Tommy Matthews 1/29/2019
Passed: Building - Slab Back Porch Troy Crews 2/7/2019
Passed: Building - Vertical Cells/Columns Tommy Matthews 2/13/2019
Passed: Building - Lintel/Tie Beam Tommy Matthews 2/13/2019
Passed: Building - Roof Decking Troy Crews 5/14/2019
Passed: Building - Framing Matt Forsyth 7/2/2019
Passed: Electrical - 2nd Rough-In Matt Forsyth 9/24/2019
Passed: Mechanical - Above Ceiling Matt Forsyth 9/24/2019
Passed: Mechanical - Rough In Matt Forsyth 9/24/2019
Passed: Plumbing/Gas - 2nd Rough-In Matt Forsyth 9/24/2019
Passed: Building - Insulation Matt Forsyth 10/14/2019
Septic Release Inspection Health Dept 4/1/2020
Passed: Electrical - Permanent Power Matt Forsyth 4/1/2020
Release to power company Matt Forsyth 4/1/2020
Failed: Building - Final Need Dedicated Recpticals Over Countertops Not Tied Into Lights Open Ground On Back Porch Matt Forsyth 12/22/2020
Passed: Building - Final Matt Forsyth 12/29/2020