Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Tommy Matthews |
11/29/2018 |
Passed: Engineering - Setbacks |
|
Tommy Matthews |
11/29/2018 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Tommy Matthews |
1/8/2019 |
Passed: Building - Slab |
|
Tommy Matthews |
1/14/2019 |
Passed: Building - Slab |
Already Done On 1-14-19 |
Troy Crews |
1/17/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Tommy Matthews |
4/16/2019 |
Failed: Building - Roof Decking |
Remove And Renail Over Back Door And At Truss T04 Over Front Porch |
Tommy Matthews |
4/16/2019 |
Failed: Building - Framing |
See Shearwall Detail Showing 2 King Studs At Each Opening Location. |
Tommy Matthews |
4/16/2019 |
Passed: Building - Framing |
Items Corrected |
Troy Crews |
5/7/2019 |
Passed: Electrical - Rough In |
|
Troy Crews |
5/7/2019 |
Passed: Mechanical - Rough In |
|
Troy Crews |
5/7/2019 |
Failed: Plumbing/Gas - Rough In |
Insulate Water Lines Near Soffit Areas Call Back In With Insulation Inspection |
Troy Crews |
5/7/2019 |
Passed: Building - Insulation |
|
Troy Crews |
5/29/2019 |
Passed: Plumbing/Gas - Rough In |
Pipes Are Insulated |
Troy Crews |
5/29/2019 |
Failed: Building - Final |
Not Complete.to Many Issues To List. |
Tommy Matthews |
8/14/2019 |
Passed: Electrical - Permanent Power |
Eh Rec'd, Need Driveway Final Rec'd |
Tommy Matthews |
8/14/2019 |
Septic Release Inspection |
|
Health Dept |
8/21/2019 |
Release to power company |
|
Tm |
8/22/2019 |
Failed: Building - Final |
Seal Refrigerant Lines,blower Door Test, Final Termite Certificate. |
Troy Crews |
12/20/2019 |
Failed: Building - Final |
Need Final Termite Cert-rec'd 1/29/20, Blower Door Test, Seal A.c. Chase Line By Outside Unit, All Rec'd |
Troy Crews |
1/23/2020 |
Passed: Building - Final |
|
Troy Crews |
5/8/2020 |