Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Tommy Matthews |
5/3/2018 |
Passed: Engineering - Setbacks |
Need Porti Potti Asap |
Tommy Matthews |
5/3/2018 |
Passed: Engineering - Initial Driveway |
|
David Mccormick |
5/4/2018 |
Passed: Plumbing/Gas - Rough In |
|
Tommy Matthews |
5/11/2018 |
Release to power company |
|
Troy Crews |
5/15/2018 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
5/16/2018 |
Passed: Building - Slab |
Contractor Uses Termite Bait System |
Troy Crews |
5/17/2018 |
Passed: Building - Roof Decking |
|
Troy Crews |
6/6/2018 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
6/6/2018 |
Rescheduled 6/19/2018:Building - Framing |
Rescheduled |
Laurie Hodson |
6/18/2018 |
Rescheduled 6/19/2018:Electrical - Rough In |
Rescheduled |
Laurie Hodson |
6/18/2018 |
Rescheduled 6/19/2018:Mechanical - Rough In |
Rescheduled |
Laurie Hodson |
6/18/2018 |
Rescheduled 6/19/2018:Plumbing/Gas - Rough In |
Rescheduled |
Laurie Hodson |
6/18/2018 |
Passed: Building - Framing |
|
Troy Crews |
6/19/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
6/19/2018 |
Passed: Mechanical - Rough In |
|
Troy Crews |
6/19/2018 |
Passed: Plumbing/Gas - Rough In |
|
Troy Crews |
6/19/2018 |
Passed: Building - Insulation |
|
Troy Crews |
6/27/2018 |
Septic Release Inspection |
|
Health Dept |
8/6/2018 |
Cancelled: Electrical - Permanent Power |
Need Elevation Letter, Elevation Letter Rec'd 8/23/18 |
Troy Crews |
8/17/2018 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
8/24/2018 |
Release to power company |
|
Troy Crews |
8/24/2018 |
Passed: Engineering - Final Driveway |
|
David Mccormick |
8/27/2018 |
Passed: Building - Final |
Check Master Bath Gfci And Gfci By Air Condenser |
Troy Crews |
9/12/2018 |
Passed: Building - Final |
Done On 9-12-18 |
Troy Crews |
12/7/2018 |