Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Dm |
12/5/2017 |
Release to power company |
|
Randy Jones |
12/12/2017 |
Temporary Power Inspection |
|
Randy Jones |
12/12/2017 |
Underslab Rough Plumbing Inspection |
|
Randy Jones |
12/12/2017 |
Temporary Power Inspection |
|
Randy Jones |
12/12/2017 |
Underslab Rough Plumbing Inspection |
|
Randy Jones |
12/12/2017 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Randy Jones |
12/12/2017 |
Passed: Electrical - Temporary Service |
|
Randy Jones |
12/12/2017 |
Slab Inspection |
|
Randy Jones |
12/18/2017 |
Slab Inspection |
|
Randy Jones |
12/18/2017 |
Passed: Building - Slab |
|
Randy Jones |
12/18/2017 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
1/30/2018 |
Failed: Building - Framing |
Anchor Bolts Green Paint, Add King Studs Both Sides Rear Window ,garage Door Header Attachment Not Per Plan |
Troy Crews |
2/23/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
2/23/2018 |
Passed: Mechanical - Rough In |
|
Troy Crews |
2/23/2018 |
Passed: Plumbing/Gas - Rough In |
|
Troy Crews |
2/23/2018 |
Passed: Building - Insulation |
|
Troy Crews |
2/28/2018 |
Passed: Building - Framing |
Items Corrected |
Troy Crews |
2/28/2018 |
Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
3/28/2018 |
Passed: Engineering - Final Driveway |
|
Dm |
4/30/2018 |
Cancelled: Electrical - Underground Rough-In |
|
Troy Crews |
4/30/2018 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
4/30/2018 |
Release to power company |
|
Laurie Hodson |
5/23/2018 |
Septic Release Inspection |
|
Health Dept |
5/23/2018 |
Failed: Building - Final |
Need Blower Door Test(rec'd 6/28/18), Step In Garage, Faucet In Bathroom |
Troy Crews |
6/25/2018 |
Passed: Building - Final |
Items Corrected |
Troy Crews |
7/13/2018 |
CERTIFICATE OF OCCUPANCY/COMPLETION DATE |
|
|
7/16/2018 |