| Inspection |
Notes |
Performed By |
Date |
| Foundation Inspection |
|
Troy Crews |
7/19/2017 |
| Setback Inspection |
|
Troy Crews |
7/19/2017 |
| Temporary Power Inspection |
|
Tommy Matthews |
7/26/2017 |
| Underslab Rough Plumbing Inspection |
|
Tommy Matthews |
7/26/2017 |
| Slab Inspection |
|
Randy Jones |
7/27/2017 |
| Slab Inspection |
|
Randy Jones |
7/27/2017 |
| Sheathing and Nailing Inspection |
|
Tommy Matthews |
8/10/2017 |
| Framing Inspection |
|
Troy Crews |
9/15/2017 |
| Electrical Rough-in- select inspection options... |
|
Troy Crews |
9/15/2017 |
| Heat & AC- |
|
Troy Crews |
9/15/2017 |
| Rough-In Plumbing Inspection |
|
Troy Crews |
9/15/2017 |
| Electrical Rough-In Inspection |
|
Troy Crews |
9/15/2017 |
| Heat and Air Duct Inspection |
|
Troy Crews |
9/15/2017 |
| Insulation Inspection |
|
Troy Crews |
9/26/2017 |
| Failed: Electrical - Permanent Power |
|
Troy Crews |
12/19/2017 |
| Failed: Electrical - Permanent Power |
Need Door Lock In Garage Entry |
Tommy Matthews |
12/29/2017 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
1/2/2018 |
| Release to power company |
|
Laurie Hodson |
1/8/2018 |
| Septic Release Inspection |
|
Health Dept |
1/8/2018 |
| Failed: Building - Final |
Need Termite Cert. Blower Door Test Traffic Stop For Garage Equipment. |
Troy Crews |
1/29/2018 |
| Final Inspection |
|
|
2/1/2018 |
| CERTIFICATE OF OCCUPANCY/COMPLETION DATE |
|
|
2/1/2018 |
| Final Inspection |
|
Troy Crews |
2/1/2018 |
| Failed: Building - Final |
Need Blower Door Test Results |
Troy Crews |
2/1/2018 |
| Passed: Building - Final |
Blower Door Test Recieved |
Troy Crews |
2/1/2018 |
| (Requested) Framing |
|
|
|
| (Requested) Electrical Rough-in |
|
|
|
| (Requested) Heat & AC-Rough-in/Duct |
|
|
|
| (Requested) Insulation |
|
|
|