Electrical - Temporary Power Service
Allows temporary power for construction use. Ref: NEC Art. 230
Inspection was completed on 2025.11.26.
Building - Footer
Inspects footing size, depth, and reinforcing steel before concrete placement. Ref: FBC 110.3(1)
Inspection was completed on 2025.11.26.
Electrical - 1st Underground Rough–In
Verifies conduit, wiring, and grounding prior to backfill. Ref: NEC Art. 300.5
Inspection was completed on 2025.12.16.
Plumbing/Gas - 1st Underground Rough–In
Inspects drainage and water piping before backfill. Ref: FBC-P 312
Inspection was completed on 2025.12.16.
Slab - Partial
Inspection was completed on 2025.12.19.
Building - Wall Sheathing
Confirms nail/screw spacing and panel installation per plans. Ref: FBC 110.3(3)
Inspection was completed on 2026.01.13.
Building - Ext Strapping/Wall Sheathing
Verifies wall sheathing, nailing, and exterior strapping per wind-load requirements. Ref: FBC 110.3, 1609
Inspection was completed on 2026.01.13.
Building - Roof Decking
Checks roof sheathing attachment and fastener pattern per FBC wind zones. Ref: FBC 110.3(3)
Inspection was completed on 2026.01.13.
Building - Framing
Reviews structural framing, load paths, fire blocking, and MEP rough-ins prior to insulation. Ref: FBC 110.3(3)
Inspection was completed on 2026.02.09.
Electrical - 2nd Rough-In
Checks wiring, panel placement, and boxes before cover-up. Ref: NEC Art. 110.3
Inspection was completed on 2026.02.09.
Plumbing/Gas - 2nd Rough-In
Reviews piping, venting, and fixtures before wall close. Ref: FBC-P 312
Inspection was completed on 2026.02.09.
Plumbing/Gas - Tub Set/Shower Pan
Verifies water-tightness and slope before tile. Ref: FBC-P 312.9
Inspection was completed on 2026.02.09.
Mechanical - Rough In
Checks ductwork, equipment location, and condensate before covering. Ref: FBC-M 603
Inspection was completed on 2026.02.09.
Building - Insulation
Verifies insulation type, R-value, and installation before drywall. Ref: FBC Energy C101.5
Inspection was completed on 2026.02.12.
City of Lake City Utilities - Lake City Utilities Tap Inspection
Conducted when required by the City to verify proper connection and availability of utility services. Ref: City of Lake City
Electrical - Permanent Power
Releases power once service equipment is complete and safe. Ref: NEC Art. 230
Building - Final
Ensures structure is complete, safe, and code-compliant before Certificate of Occupancy. Ref: FBC 110.5