Electrical - 1st Underground Rough–In
Verifies conduit, wiring, and grounding prior to backfill. Ref: NEC Art. 300.5
Plumbing/Gas - 1st Underground Rough–In
Inspects drainage and water piping before backfill. Ref: FBC-P 312
Inspection was completed on 2025.10.01.
Plumbing/Gas - 2nd Rough-In
Reviews piping, venting, and fixtures before wall close. Ref: FBC-P 312
Missing required documentation.
Electrical - 2nd Rough-In
Checks wiring, panel placement, and boxes before cover-up. Ref: NEC Art. 110.3
Missing required documentation.
Building - Ext Strapping/Wall Sheathing
Verifies wall sheathing, nailing, and exterior strapping per wind-load requirements. Ref: FBC 110.3, 1609
Missing required documentation. Missing required documents.
Building - Footer
Inspects footing size, depth, and reinforcing steel before concrete placement. Ref: FBC 110.3(1)
Inspection was completed on 2025.09.05.
Building - Framing
Reviews structural framing, load paths, fire blocking, and MEP rough-ins prior to insulation. Ref: FBC 110.3(3)
Missing required documentation.
Building - Insulation
Verifies insulation type, R-value, and installation before drywall. Ref: FBC Energy C101.5
Missing required documentation.
Building - Monolithic Slab
Inspects reinforcement, vapor barrier, termite treatment, and plumbing prior to pour. Ref: FBC 110.3(1)
Building - Roof Decking
Checks roof sheathing attachment and fastener pattern per FBC wind zones. Ref: FBC 110.3(3)
Missing required documentation.
Mechanical - Rough In
Checks ductwork, equipment location, and condensate before covering. Ref: FBC-M 603
Missing required documentation.
Building - Slab
Ensures proper base, vapor barrier, reinforcing, and termite treatment before pour. Ref: FBC 110.3(1)
Building - Strapping
Reviews hurricane straps, anchors, and connections, for uplift resistance. Ref: FBC 1609
Missing required documentation.
Electrical - Temporary Power Service
Allows temporary power for construction use. Ref: NEC Art. 230
Inspection was completed on 2025.10.01.
Plumbing/Gas - Tub Set/Shower Pan
Verifies water-tightness and slope before tile. Ref: FBC-P 312.9
Missing required documentation.
Building - Wall Sheathing
Confirms nail/screw spacing and panel installation per plans. Ref: FBC 110.3(3)
Missing required documentation.
Building - Final
Ensures structure is complete, safe, and code-compliant before Certificate of Occupancy. Ref: FBC 110.5
Assessment is owed.
Electrical - Permanent Power
Releases power once service equipment is complete and safe. Ref: NEC Art. 230
Missing required documentation.