Plumbing/Gas - 1st Underground Rough–In
Plumbing/Gas - 2nd Rough-In
Electrical - 2nd Rough-In
Checks wiring, panel placement, and boxes before cover-up. Ref: NEC Art. 110.3
Electrical - Above Ceiling
Inspects conduit, junctions, and wiring above ceilings before close-up. Ref: NEC Art. 300.11
Fire - Aboveground Hydro - Sprinkler
Pressure test of sprinkler piping aboveground. Ref: NFPA 13 §25.2
Fire - Aboveground Sprinkler - Visual (On Site)
Building - Ext Strapping/Wall Sheathing
Verifies wall sheathing, nailing, and exterior strapping per wind-load requirements. Ref: FBC 110.3, 1609
Fire - Fire Final
Building - Fire Rated Wall
Confirms fire-related wall assemblies meet UL/FBC details and penetrations are properly sealed. Ref: FBC 703
Fire - Fire Rated Wall
Building - Footer
Inspects footing size, depth, and reinforcing steel before concrete placement. Ref: FBC 110.3(1)
Building - Framing
Reviews structural framing, load paths, fire blocking, and MEP rough-ins prior to insulation. Ref: FBC 110.3(3)
Inspection was completed on 2025.08.29.
Mechanical - Framing/Fire Damper
Fire - Fuel Tank Installation
Fire - Hydrant Flow Test
Building - Insulation
Verifies insulation type, R-value, and installation before drywall. Ref: FBC Energy C101.5
Plumbing/Gas - Interceptor
Mechanical - Kitchen Hood
Fire - Kitchen Hood – Fire Suppression Test
Building - Lath/Stucco
Checks stucco lath, weep screeds, and moisture barriers before application. Ref: FBC 110.3
Mechanical - Light Test
Fire - Light Test
Building - Lintel/Tie Beam
Ensures lintel/tie beam reinforcing steel and anchorage are correct before pour. Ref: FBC 110.3
Building - Masonry Wall Reinforcing
Confirms vertical and horizontal reinforcing per engineered plans. Ref: FBC 2122.2
Plumbing/Gas - Medical Gas
Fire - Operational Test - Alarm System
Fire - Operational Test - Chemical/Gaseous Agent
Fire - Operational Test - Fire Pump
Fire - Operational Test - Sprinkler/Standpipe
Mechanical - Performance Test and Balance
Electrical - Permanent Power
Releases power once service equipment is complete and safe. Ref: NEC Art. 230
Mechanical - Pipe Pressure Test
Plumbing/Gas - Rain Leader
Building - Rated Assembly Fastening
Verifies fastening and components for fire-rated walls, ceilings, or roofs. Ref: FBC 703
Mechanical - Refrigeration
Building - Roof Decking
Checks roof sheathing attachment and fastener pattern per FBC wind zones. Ref: FBC 110.3(3)
Mechanical - Rough In
Plumbing/Gas - Sanitary
Building - Slab
Ensures proper base, vapor barrier, reinforcing, and termite treatment before pour. Ref: FBC 110.3(1)
Fire - Sprinkler System Alteration
Plumbing/Gas - Tub Set/Shower Pan
Fire - Underground Main - Flush
Fire - Underground Main - Hydro
Fire - Underground Main - Visual
Building - Vertical Cells/Columns
Checks filled masonry cells or columns for reinforcing and grout. Ref: FBC 2122.2
Building - Wall Sheathing
Confirms nail/screw spacing and panel installation per plans. Ref: FBC 110.3(3)
Plumbing/Gas - Water Pipe
Building - Window Attachment
Verifies fastening of windows/doors for impact and wind load compliance. Ref: FBCR 609
Engineering - Zoning Final
Building - Final
Ensures structure is complete, safe, and code-compliant before Certificate of Occupancy. Ref: FBC 110.5