Electrical - Temporary Power Service
Allows temporary power for construction use. Ref: NEC Art. 230
Inspection was completed on 2025.10.03.
Electrical - 1st Underground Rough–In
Verifies conduit, wiring, and grounding prior to backfill. Ref: NEC Art. 300.5
Inspection was completed on 2025.10.08.
Plumbing/Gas - 1st Underground Rough–In
Inspects drainage and water piping before backfill. Ref: FBC-P 312
Inspection was completed on 2025.10.08.
Building - Monolithic Slab
Inspects reinforcement, vapor barrier, termite treatment, and plumbing prior to pour. Ref: FBC 110.3(1)
Inspection was completed on 2025.10.10.
Building - Masonry Wall Reinforcing
Confirms vertical and horizontal reinforcing per engineered plans. Ref: FBC 2122.2
Building - Vertical Cells/Columns
Checks filled masonry cells or columns for reinforcing and grout. Ref: FBC 2122.2
Building - Lintel/Tie Beam
Ensures lintel/tie beam reinforcing steel and anchorage are correct before pour. Ref: FBC 110.3
Building - Roof Decking
Checks roof sheathing attachment and fastener pattern per FBC wind zones. Ref: FBC 110.3(3)
Inspection was completed on 2025.10.20.
Building - Strapping
Reviews hurricane straps, anchors, and connections, for uplift resistance. Ref: FBC 1609
Inspection was completed on 2025.10.20.
Building - Wall Sheathing
Confirms nail/screw spacing and panel installation per plans. Ref: FBC 110.3(3)
Inspection was completed on 2025.10.20.
Building - Framing
Reviews structural framing, load paths, fire blocking, and MEP rough-ins prior to insulation. Ref: FBC 110.3(3)
Inspection was completed on 2025.10.27.
Mechanical - Rough In
Checks ductwork, equipment location, and condensate before covering. Ref: FBC-M 603
Inspection was completed on 2025.10.27.
Plumbing/Gas - Tub Set/Shower Pan
Verifies water-tightness and slope before tile. Ref: FBC-P 312.9
Inspection was completed on 2025.10.27.
Plumbing/Gas - 2nd Rough-In
Reviews piping, venting, and fixtures before wall close. Ref: FBC-P 312
Inspection was completed on 2025.10.27.
Electrical - 2nd Rough-In
Checks wiring, panel placement, and boxes before cover-up. Ref: NEC Art. 110.3
Inspection was completed on 2025.10.27.
Building - Insulation
Verifies insulation type, R-value, and installation before drywall. Ref: FBC Energy C101.5
Inspection was completed on 2025.10.29.
Building - Lath/Stucco
Checks stucco lath, weep screeds, and moisture barriers before application. Ref: FBC 110.3
Electrical - Permanent Power
Releases power once service equipment is complete and safe. Ref: NEC Art. 230
Building - Final
Ensures structure is complete, safe, and code-compliant before Certificate of Occupancy. Ref: FBC 110.5
Assessment is owed.