Electrical - 1st Underground Rough–In
Verifies conduit, wiring, and grounding prior to backfill. Ref: NEC Art. 300.5
Inspection was completed on 2025.05.08.
Plumbing/Gas - 1st Underground Rough–In
Plumbing/Gas - 2nd Rough-In
Inspection was completed on 2025.05.09.
Electrical - 2nd Rough-In
Checks wiring, panel placement, and boxes before cover-up. Ref: NEC Art. 110.3
Inspection was completed on 2025.05.09.
Engineering - D.O.T Final Driveway
Please call to schedule these inspections due to a Flood Harzard Area.
Building - Ext Strapping/Wall Sheathing
Verifies wall sheathing, nailing, and exterior strapping per wind-load requirements. Ref: FBC 110.3, 1609
Inspection was completed on 2024.09.06.
Building - Fire Rated Wall
Confirms fire-related wall assemblies meet UL/FBC details and penetrations are properly sealed. Ref: FBC 703
Building - Footer
Inspects footing size, depth, and reinforcing steel before concrete placement. Ref: FBC 110.3(1)
Inspection was completed on 2023.11.13.
Building - Framing
Reviews structural framing, load paths, fire blocking, and MEP rough-ins prior to insulation. Ref: FBC 110.3(3)
Building - Insulation
Verifies insulation type, R-value, and installation before drywall. Ref: FBC Energy C101.5
Building - Lath/Stucco
Checks stucco lath, weep screeds, and moisture barriers before application. Ref: FBC 110.3
Building - Lintel/Tie Beam
Ensures lintel/tie beam reinforcing steel and anchorage are correct before pour. Ref: FBC 110.3
Building - Masonry Wall Reinforcing
Confirms vertical and horizontal reinforcing per engineered plans. Ref: FBC 2122.2
Please call to schedule these inspections due to a Flood Harzard Area.
Building - Monolithic Slab
Inspects reinforcement, vapor barrier, termite treatment, and plumbing prior to pour. Ref: FBC 110.3(1)
Please call to schedule these inspections due to a Flood Harzard Area.
Building - Rated Assembly Fastening
Verifies fastening and components for fire-rated walls, ceilings, or roofs. Ref: FBC 703
Building - Roof Decking
Checks roof sheathing attachment and fastener pattern per FBC wind zones. Ref: FBC 110.3(3)
Inspection was completed on 2024.09.06.
Mechanical - Rough In
Inspection was completed on 2025.05.09.
Building - Slab
Ensures proper base, vapor barrier, reinforcing, and termite treatment before pour. Ref: FBC 110.3(1)
Please call to schedule these inspections due to a Flood Harzard Area.
Building - Strapping
Reviews hurricane straps, anchors, and connections, for uplift resistance. Ref: FBC 1609
Electrical - Temporary Power Service
Allows temporary power for construction use. Ref: NEC Art. 230
Inspection was completed on 2025.06.16.
Plumbing/Gas - Tub Set/Shower Pan
Building - Vertical Cells/Columns
Checks filled masonry cells or columns for reinforcing and grout. Ref: FBC 2122.2
Inspection was completed on 2024.02.06.
Building - Wall Sheathing
Confirms nail/screw spacing and panel installation per plans. Ref: FBC 110.3(3)
Building - Window Attachment
Verifies fastening of windows/doors for impact and wind load compliance. Ref: FBCR 609
Building - Final
Ensures structure is complete, safe, and code-compliant before Certificate of Occupancy. Ref: FBC 110.5
Please call to schedule these inspections due to a Flood Harzard Area.
Electrical - Permanent Power
Releases power once service equipment is complete and safe. Ref: NEC Art. 230
Inspection was completed on 2025.06.02.