Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 4238 SW STATE ROAD 247
LAKE CITY, FL 32024
Parcel #: 03046-003
Acres: 1.02
Owner: Buchner Ronald,
Subdivision:
Zoning: RR
Flood Zone: X
District: 3
Application #: 61584
Permit #: 000047626
Related Permit:
Submitted: Thursday, June 15, 2023
Issued: Monday, July 10, 2023
Expires: Monday, December 11, 2023
Completed: Monday, December 11, 2023
Status: Completed
Septic Release? Yes
Notes:
MFE TO BE 12" ABOVE ADJACENT GRADE FOR ENTIRE PERMIETER OF STRUCTURE
Job Details
Finished floor requirement
Fema map number 12023C0289D
What is the power service for? Other
Other job details: Installation of a powerwall battery storage system for existing solar and powerwall battery storage system. Permit #000050168
Power Company Clay Electric
Septic # (00-0000) or (X00-000) x25-000
Electrical Code Edition 2020 National Electrical Code
Meter or Account: Account
Meter or Account #: 7230386
Number of requested AMPS for electrical service: 200
Is the power service? Upgrading Existing Service
Residential or Commercial? Residential
Review Notes
6/15/2023 Point Review - Reviewed
6/22/2023 Plan Review - Corrections Needed
6/22/2023 Plan Review - Building Approved
6/22/2023 Plan Review - Electrical Approved
6/22/2023 Plan Review - Mechanical Approved
6/22/2023 Plan Review - Plumbing Approved
6/22/2023 Plan Review - Fuel/Gas Approved
6/22/2023 Plan Review - Reviewed
6/27/2023 Zoning Review - Reviewed
6/27/2023 Final Review - Processing
6/27/2023 Zoning Review - Reviewed
7/10/2023 Final Review - Reviewed
7/10/2023 Final Review - Payment Needed
7/10/2023 Permit Issued
Contractors
Name/ Business License Title Role
Everton D Ruddock
D&s Lighting Inc
EC13003800 Electrical Contractor Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Electrical - Temporary Service Matt Forsyth 7/18/2023
Release to power company Matt Forsyth 7/18/2023
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 7/18/2023
Passed: Building - Monolithic Slab Matt Forsyth 7/24/2023
Passed: Engineering - Setbacks Matt Forsyth 7/24/2023
Passed: Building - Wall Sheathing Matt Forsyth 8/10/2023
Passed: Building - Framing Attic Access Not Framed. Post Base All Nail Holes With 16 Penny Nails Matt Forsyth 9/5/2023
Passed: Building - Roof Decking Matt Forsyth 9/5/2023
Passed: Building - Strapping Strapping Installed Inside Sheathing On Gables Matt Forsyth 9/5/2023
Passed: Electrical - 2nd Rough-In Troy Crews 10/13/2023
Passed: Mechanical - Rough In Troy Crews 10/13/2023
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 10/13/2023
Passed: Building - Insulation Walls Only Matt Forsyth 10/17/2023
Septic Release Inspection Health Dept 11/7/2023
Passed: Electrical - Permanent Power Matt Forsyth 11/9/2023
Release to power company Matt Forsyth 11/9/2023
Passed: Plumbing/Gas - Tub Set/Shower Pan Matt Forsyth 11/9/2023
Passed: Building - Final Working On Blower Door And Final Termite Treatment Matt Forsyth 12/8/2023
Certificate-Release Certificate All Doc Rec Matt Forsyth 12/11/2023
Documents
File Name Date File Size