Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
Passed By Kevin Powell |
Private Provider |
5/3/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Passed By Kevin Powell |
Private Provider |
5/3/2024 |
Passed: Building - Monolithic Slab |
Passed By Kevin Powell |
Private Provider |
5/7/2024 |
Passed: Engineering - Setbacks |
Passed By Kevin Powell |
Private Provider |
5/7/2024 |
Release to power company |
|
Private Provider |
5/7/2024 |
Passed: Building - Roof Decking |
Passed By Kevin Powell |
Private Provider |
5/17/2024 |
Release to power company |
Re-release Power To Correct Power Company |
Neonta Anderson |
6/10/2024 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
Passed By Kevin Powell |
Private Provider |
7/5/2024 |
Passed: Electrical - 2nd Rough-In |
Passed By Kevin Powell |
Private Provider |
7/5/2024 |
Passed: Building - Ext Strapping/Wall Sheathing |
Passed By Kevin Powell |
Private Provider |
7/5/2024 |
Passed: Building - Strapping |
Passed By Kevin Powell |
Private Provider |
7/5/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
Passed By Kevin Powell |
Private Provider |
7/5/2024 |
Passed: Mechanical - Rough In |
Passed By Kevin Powell |
Private Provider |
7/5/2024 |
Passed: Building - Framing |
Passed By Kevin Powell |
Private Provider |
7/5/2024 |
Passed: Building - Insulation |
Passed By Kevin Powell |
Private Provider |
7/19/2024 |
Passed: Electrical - Permanent Power |
Passed By Kevin Powell |
Private Provider |
8/29/2024 |
Cancelled: Electrical - Permanent Power |
|
Melissa Garber |
10/23/2024 |
Release to power company |
|
Private Provider |
10/23/2024 |
Certificate-Release Certificate |
|
Private Provider |
1/28/2025 |
Passed: Building - Final |
Passed By Kevin Powell |
Private Provider |
1/28/2025 |
Septic Release Inspection |
|
Health Dept |
2/5/2025 |
(Requested) Building-Wall Sheathing |
|
|
|