Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Need Compaction At Slab |
Anthony Aslan |
10/23/2024 |
Passed: Building - Monolithic Slab |
Check For Bait System On Final, Send Pictures Of Porch Footer Steel And Ground Wire To Footer Steel Prior To Pour. |
Troy Crews |
10/30/2024 |
Passed: Engineering - Setbacks |
|
Troy Crews |
10/30/2024 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
11/15/2024 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
11/15/2024 |
Failed: Building - Ext Strapping/Wall Sheathing |
Strapping Not Complete |
Anthony Aslan |
11/15/2024 |
Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
12/3/2024 |
Failed: Mechanical - Rough In |
Strapping Missing On Exhaust Venting
( Insulation Installed On Inside Of Supply Plenum ) |
Anthony Aslan |
12/3/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
12/3/2024 |
Failed: Plumbing/Gas - Tub Set/Shower Pan |
Tub Missing, No Water In Tubs |
Anthony Aslan |
12/3/2024 |
Passed: Building - Insulation |
Tube Has Water, Master Tub Will Be Set After Tile |
Anthony Aslan |
12/10/2024 |
Passed: Mechanical - Rough In |
Corrections Made |
Anthony Aslan |
12/10/2024 |
Cancelled: Electrical - 2nd Rough-In |
|
Anthony Aslan |
3/27/2025 |
Septic Release Inspection |
|
Health Dept |
4/7/2025 |
Passed: Electrical - Permanent Power |
Need Driveway Final |
Anthony Aslan |
4/10/2025 |
Cancelled: Engineering - D.O.T Final Driveway |
|
Melissa Garber |
5/7/2025 |
Release to power company |
|
Melissa Garber |
5/13/2025 |
Release to power company |
Resend To Clay |
Emaleigh Williams |
5/28/2025 |
Passed: Building - Final |
All Requirements Met-- Ok To Issue Co-- 7.21.25 Mg |
Anthony Aslan |
7/15/2025 |