| Cancelled: Building - Roof Decking |
|
Anthony Aslan |
5/5/2022 |
| Cancelled: Building - Vertical Cells/Columns |
|
Anthony Aslan |
5/5/2022 |
| Cancelled: Building - Wall Sheathing |
|
Anthony Aslan |
5/5/2022 |
| Failed: Building - Footer |
Not Ready |
Anthony Aslan |
5/5/2022 |
| Cancelled: Engineering - Setbacks |
|
Anthony Aslan |
5/5/2022 |
| Cancelled: Building - Monolithic Slab |
|
Anthony Aslan |
5/5/2022 |
| Passed: Engineering - Spot Check |
Need To Modify Plans To Match Existing Conditions. |
Troy Crews |
10/17/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
12/22/2022 |
| Passed: Building - Framing |
|
Troy Crews |
12/22/2022 |
| Passed: Building - Strapping |
|
Troy Crews |
12/22/2022 |
| Passed: Electrical - 2nd Rough-In |
Add Wiring For Smoke Detectors To Tie Together |
Troy Crews |
2/8/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Adjust Washer Riser To 30 Inches. |
Troy Crews |
2/8/2023 |
| Cancelled: Engineering - Setbacks |
|
Gary Pitzer |
3/8/2023 |
| Passed: Building - Footer |
Slab And Two Deep Holes With Steel Wire And Rebar |
Gary Pitzer |
3/8/2023 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
3/17/2023 |
| Passed: Building - Insulation |
|
Troy Crews |
4/21/2023 |
| Passed: Engineering - Spot Check |
Project Awaiting Railing |
Troy Crews |
10/18/2023 |
| Passed: Building - Final |
Need Blower Door (rec'd) And Termite For Co (rec'd)-- Co To Be Issued Once Assessments Are Paid |
Troy Crews |
3/8/2024 |
| Certificate-Release Certificate |
|
Troy Crews |
3/15/2024 |