Solar Power System
Permit
| Application #: | 58573 |
| Permit #: |
000046486 |
| Related Permit: |
|
| Submitted: | Tuesday, January 3, 2023 |
| Issued: | Wednesday, February 8, 2023 |
| Expires: | Wednesday, April 26, 2023 |
| Completed: | Wednesday, April 26, 2023 |
| Status: |
Completed |
| Septic Release? |
N/A |
Job Details
| Finished floor requirement |
|
| Fema map number |
12023C0260C |
| PV Type |
Stand Alone PV System without Batteries- (DC to AC without utility connection) |
| Grounding |
N.E.C. Chapter 690 |
| AC Options |
Exposed |
| AC Options (Cont..) |
THWN-2 |
| Building Code Edition |
2020 Florida Building Code 7th Edition and 2017 National Electrical Code |
| Power Company |
Florida Power and Light |
| Residential or Commercial? |
Residential |
| Where are the panels mounted? |
Ground Mounted |
| Service Amps |
200 |
Review Notes
| 1/3/2023 |
Application pending. |
| 1/3/2023 |
Application submitted by applicant. |
| 1/9/2023 |
Point Review - Processing |
| 1/10/2023 |
Plan Review - Reviewed |
| 1/12/2023 |
Zoning Review - Documents Required |
| 1/17/2023 |
Zoning Review - Documents Required |
| 1/23/2023 |
Zoning Review - Documents Required |
| 1/27/2023 |
Zoning Review - Documents Required |
| 2/6/2023 |
Zoning Review - Reviewed |
| 2/6/2023 |
Final Review - Reviewed |
| 2/6/2023 |
Final Review - Reviewed |
| 2/7/2023 |
Final Review - Payment Needed |
| 2/8/2023 |
Permit Issued |
| 4/6/2023 |
Final Review - Payment Needed |
| 4/6/2023 |
Plan Review - Reviewed |
Contractors
| Name / Business |
License |
Title |
Role |
Ronnie Padgett Adt Solar Llc
County License & State License Expired. |
EC13001242 |
Cert. Electrical |
Contractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
3/13/2023 |
| Failed: Building - Footer |
Not Complete |
Matt Forsyth |
3/13/2023 |
| Passed: Building - Footer |
|
Matt Forsyth |
3/20/2023 |
| Passed: Engineering - Setbacks |
Setback Checked |
Matt Forsyth |
3/20/2023 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
4/6/2023 |
| Release to power company |
|
Matt Forsyth |
4/6/2023 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
4/26/2023 |
| Release to power company |
|
Matt Forsyth |
4/26/2023 |
| Passed: Solar - Solar Final |
|
Matt Forsyth |
4/26/2023 |
| Release to power company |
|
Matt Forsyth |
4/26/2023 |