| 4/25/2025 |
Application submitted by applicant. |
| 4/25/2025 |
Pending Public Works Application Approval |
| 5/1/2025 |
Application Approved by Public Works |
| 5/7/2025 |
Final Review - Payment Needed |
| 5/8/2025 |
Pending initial driveway inspection |
| 5/8/2025 |
Final Review - Complete |
| 6/10/2025 |
Final Review - Documents Required |
| 6/11/2025 |
Final Review - Corrections Needed |
| 6/15/2025 |
Final Review - Corrections Needed |
| 6/18/2025 |
Final Review - Corrections Needed |
| 6/20/2025 |
Final Review - Corrections Needed |
| 6/23/2025 |
Final Review - Corrections Needed |
| 6/24/2025 |
Final Review - Corrections Needed |
| 7/1/2025 |
Final Review - Corrections Needed |
| 7/11/2025 |
Final Review - Corrections Needed |
| 7/14/2025 |
Final Review - Corrections Needed |
| 7/29/2025 |
Final Review - Corrections Needed |
| 8/2/2025 |
Final Review - Corrections Needed |
| 8/14/2025 |
Final Review - Corrections Needed |
| 8/18/2025 |
Final Review - Corrections Needed |
| 9/1/2025 |
Final Review - Corrections Needed |
| 9/4/2025 |
Final Review - Corrections Needed |
| 9/8/2025 |
Final Review - Corrections Needed |
| 9/11/2025 |
Final Review - Corrections Needed |
| 9/12/2025 |
Final Review - Corrections Needed |
| 9/16/2025 |
Final Review - Corrections Needed |
| 9/17/2025 |
Final Review - Corrections Needed |
| 9/23/2025 |
Final Review - Corrections Needed |
| 9/25/2025 |
Final Review - Corrections Needed |
| 10/15/2025 |
Final Review - Corrections Needed |
| 10/25/2025 |
Final Review - Corrections Needed |
| 12/2/2025 |
Application Status Update Notification |
| 1/6/2026 |
Permit Issued |