Request to Schedule Inspections
Enter your permit number, then tell us what you’d like to do.
New Residential Construction
513 SW MEADOWLANDS DR
LAKE CITY, FL 32024
2
Date & contact
Tell us when you need the inspector and how to reach you.
3
Select inspections
Check each inspection you need. An inspection that is already scheduled can’t be requested again until it is cancelled.
* The final inspection cannot be requested because the assessment fees are owed on this property. Other inspections can still be requested.
-
Allows temporary power for construction use. Ref: NEC Art. 230
Inspection was completed on 2025.10.14.
-
Verifies location, layout, culvert size, and grade before driveway construction begins.
-
Inspects footing size, depth, and reinforcing steel before concrete placement. Ref: FBC 110.3(1)
Inspection was completed on 2026.03.10.
-
Approves finished driveway, verifying pavement, culvert, drainage, mitered ends, and safety compliance. Ref: Columbia County LDR 4.2.3
Assessment is owed.
Initial Driveway must be passed prior to scheduling.Initial Driveway must be passed on a Right-of-Way Access/Driveway prior to scheduling.
-
Verifies conduit, wiring, and grounding prior to backfill. Ref: NEC Art. 300.5
-
Inspects drainage and water piping before backfill. Ref: FBC-P 312
Inspection was completed on 2026.04.23.
-
Ensures proper base, vapor barrier, reinforcing, and termite treatment before pour. Ref: FBC 110.3(1)
Inspection was completed on 2026.05.14.
-
Checks filled masonry cells or columns for reinforcing and grout. Ref: FBC 2122.2
Inspection was completed on 2026.07.14.
-
Confirms vertical and horizontal reinforcing per engineered plans. Ref: FBC 2122.2
-
Ensures lintel/tie beam reinforcing steel and anchorage are correct before pour. Ref: FBC 110.3
Inspection was completed on 2026.07.14.
-
Checks roof sheathing attachment and fastener pattern per FBC wind zones. Ref: FBC 110.3(3)
Inspection was completed on 2026.10.20.
-
Reviews piping, venting, and fixtures before wall close. Ref: FBC-P 312
-
Verifies water-tightness and slope before tile. Ref: FBC-P 312.9
-
Checks ductwork, equipment location, and condensate before covering. Ref: FBC-M 603
-
Checks wiring, panel placement, and boxes before cover-up. Ref: NEC Art. 110.3
-
Reviews structural framing, load paths, fire blocking, and MEP rough-ins prior to insulation. Ref: FBC 110.3(3)
-
Verifies insulation type, R-value, and installation before drywall. Ref: FBC Energy C101.5
-
Checks stucco lath, weep screeds, and moisture barriers before application. Ref: FBC 110.3
-
Releases power once service equipment is complete and safe. Ref: NEC Art. 230
-
Ensures structure is complete, safe, and code-compliant before Certificate of Occupancy. Ref: FBC 110.5
Assessment is owed.
Enter a permit number above to see the inspections available for it.
- 1 Choose inspections
- 2 Review & confirm
- 3 Done
Confirm your request: Schedule Inspections
Please check the details below. Nothing is sent until you confirm.
- Permit number
- Inspection date
- Contact phone
- Special instructions
- Inspections
- 1 Choose inspections
- 2 Review & confirm
- 3 Done
Your request has been submitted
Building and Zoning has received it. You can request or cancel more inspections at any time.
Loading inspections…