Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Setbacks |
|
Gary Pitzer |
12/5/2024 |
Passed: Building - Footer |
|
Gary Pitzer |
12/5/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Dwv, No Clean Out |
Gary Pitzer |
1/29/2025 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
2/3/2025 |
Release to power company |
|
Matt Forsyth |
2/3/2025 |
Failed: Building - Slab |
All Hooked Bars Need To Be Properly Bent Down Into The Slab All Perimeter Number 5 Bar Needs To Be Chaired Up Minimum Three Quarters Of An Inch Away From Any
surface For Proper Concrete Consolidation
|
Matt Forsyth |
2/7/2025 |
Passed: Building - Slab |
|
Matt Forsyth |
2/10/2025 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
3/13/2025 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
3/13/2025 |
Passed: Building - Framing |
|
Gary Pitzer |
4/7/2025 |
Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
4/7/2025 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
4/14/2025 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
4/14/2025 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
4/14/2025 |
Passed: Building - Insulation |
Wall Insulation Only Inspected |
Matt Forsyth |
4/22/2025 |
Passed: Electrical - Permanent Power |
Septic Needed |
Matt Forsyth |
6/4/2025 |
Release to power company |
All Requirements Met To Release Power-- 6.20.25 Mg |
Melissa Garber |
6/20/2025 |
Septic Release Inspection |
|
Health Dept |
6/20/2025 |
Passed: Building - Final |
Blower Door Submitted And Reviewed Final Termite Treatment Documentedfinal Inspection Complete. Permit Under Office Review For Co Eligibility. |
Matt Forsyth |
8/8/2025 |
Passed: Certificate-Release Certificate |
Rec'd Blower Door And Termite |
Matt Forsyth |
8/12/2025 |