Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Jones, Richard |
11/2/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Put Pressure Back On Water Lines Prior To Mono Slab Inspection |
Troy Crews |
11/2/2021 |
Passed: Building - Slab |
House Only |
Troy Crews |
11/8/2021 |
Passed: Building - Slab |
Recommend Expansion Material At Existing House Slab. |
Troy Crews |
11/15/2021 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
11/29/2021 |
Release to power company |
|
Matt Forsyth |
11/29/2021 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
1/4/2022 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
1/4/2022 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
1/12/2022 |
Passed: Building - Framing |
|
Matt Forsyth |
1/12/2022 |
Passed: Building - Strapping |
|
Matt Forsyth |
1/12/2022 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
1/14/2022 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
1/14/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/14/2022 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
Tub Water Test Performed |
Matt Forsyth |
1/14/2022 |
Passed: Building - Insulation |
All Foam Will Need Fresh Air With Damper On A.c. |
Troy Crews |
1/19/2022 |
Passed: Building - Insulation |
Already Passed 1-19-22 |
Troy Crews |
1/19/2022 |
Passed: Engineering - Initial Driveway |
|
Smith, Blake |
1/27/2022 |
Passed: Electrical - Permanent Power |
Need Culvert Inspection And Final Septic |
Troy Crews |
3/14/2022 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
3/24/2022 |
Release to power company |
|
Melissa Garber |
3/29/2022 |
Septic Release Inspection |
|
Health Dept |
3/29/2022 |
Rescheduled 4/7/2022:Building - Final |
|
Matt Forsyth |
4/6/2022 |
Passed: Building - Final |
|
Matt Forsyth |
4/7/2022 |