Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
3/4/2021 |
Failed: Engineering - Final Driveway |
Needs Concrete Mitred Ends Poured,and 4 Inches Of Limerock On Top Cover. |
Mccormick, David |
3/31/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Will Need Compaction Test On Soil |
Matt Forsyth |
4/9/2021 |
Passed: Building - Slab |
Fibermesh Concrete |
Matt Forsyth |
4/14/2021 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
6/25/2021 |
Release to power company |
|
Troy Crews |
6/25/2021 |
Failed: Building - Roof Decking |
All Nails In Roof Sheating That Missed A Framing Member To Be Removed And Renailed. |
Matt Forsyth |
7/12/2021 |
Failed: Building - Wall Sheathing |
Nails Missing Framing Member In Wall To Be Removed And Renailed. Wall Sheeting On North Wall Bowed Out |
Matt Forsyth |
7/12/2021 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
7/12/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
7/12/2021 |
Failed: Plumbing/Gas - 2nd Rough-In |
Water Supply Lines Need Relieving Arch Coming Through Wall.(to Prevent Line From Kinking |
Matt Forsyth |
7/12/2021 |
Failed: Building - Framing |
Plans Call For 2 By 10 Header Framing Members,carpenters Used Box Beam Header Technique. Need Letter From Engineer That This
is Acceptable. |
Matt Forsyth |
7/12/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
Item Addressed With Plumbing Contractor |
Matt Forsyth |
7/12/2021 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
7/16/2021 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
7/16/2021 |
Passed: Building - Framing |
Box Beams Acceptable |
Matt Forsyth |
7/27/2021 |
Passed: Building - Insulation |
|
Matt Forsyth |
7/27/2021 |
Septic Release Inspection |
|
Health Dept |
9/23/2021 |
Failed: Electrical - Permanent Power |
Need Conduit For Service Entrance Run To Meter Can Also Driveway Release |
Matt Forsyth |
9/29/2021 |
Passed: Electrical - Permanent Power |
Need Driveway Released |
Matt Forsyth |
10/25/2021 |
Failed: Engineering - Final Driveway |
There Will Have To Be Concrete Mitered 3nds With 6x6 Welded Wire Or Rebar Or Culvert Bolts In Concrete For This Culvert To Pass Inspection. This Is Explained In The Culvert Permit. |
Jones, Richard |
11/12/2021 |
Failed: Engineering - Final Driveway |
There Are No Concrete Mitered Ends As Specified In Permit. This Driveway Will Not Pass Inspection Unless It Is Built To County Requirements As Specified In Requirements On Permit. |
Jones, Richard |
11/17/2021 |
Release to power company |
|
Melissa Garber |
12/8/2021 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
12/8/2021 |
Failed: Building - Final |
Need Final Termite Treatment, Also Several Recepticals Need To Be Looked That Are Not Reseting Need Labels In Panel Where To Reset Recept.if Not In Panel Box Assessment Fees Need To Be Paid |
Matt Forsyth |
1/20/2022 |
Failed: Building - Final |
Electrical Work Still Needs Attention |
Matt Forsyth |
1/28/2022 |
Failed: Building - Final |
Refrigerator Receptacle Would Not Trip Out |
Matt Forsyth |
2/4/2022 |
Passed: Building - Final |
|
Matt Forsyth |
2/11/2022 |