Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
3/1/2021 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
3/4/2021 |
Release to power company |
|
Matt Forsyth |
3/4/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Waste Only |
Troy Crews |
4/13/2021 |
Failed: Building - Slab |
Rod Chairs No More Than 48"oc. One Vent Stack To Close To Form Board 3/4 Min |
Matt Forsyth |
4/16/2021 |
Passed: Building - Slab |
|
Matt Forsyth |
4/21/2021 |
Passed: Building - Footer |
Front And Back Porchs |
Matt Forsyth |
5/20/2021 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
5/20/2021 |
Passed: Building - Framing |
|
Troy Crews |
10/8/2021 |
Passed: Building - Roof Decking |
|
Troy Crews |
10/8/2021 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
10/8/2021 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
11/9/2021 |
Failed: Mechanical - Rough In |
No Work Done |
Matt Forsyth |
11/9/2021 |
Failed: Plumbing/Gas - 2nd Rough-In |
2nd Floor Plumbing Needs Water Test |
Matt Forsyth |
11/9/2021 |
Failed: Mechanical - Rough In |
Need Gaskets On Hv Ac Boots Will Check At Insulation Inspection |
Matt Forsyth |
11/19/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
11/19/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
12/9/2021 |
Passed: Building - Insulation |
Walls Only |
Matt Forsyth |
12/9/2021 |
Passed: Electrical - Permanent Power |
Need Septic Release |
Matt Forsyth |
2/3/2022 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
2/17/2022 |
Release to power company |
Environmental Health Power Release Rec'd
2.25.22 |
Matt Forsyth |
2/25/2022 |
Septic Release Inspection |
|
Health Dept |
2/25/2022 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
3/1/2022 |
Release to power company |
|
Matt Forsyth |
3/1/2022 |
Passed: Building - Final |
|
Matt Forsyth |
4/4/2022 |