Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
2/23/2021 |
Passed: Building - Footer |
|
Matt Forsyth |
2/26/2021 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
2/26/2021 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
2/26/2021 |
Release to power company |
|
Matt Forsyth |
2/26/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
3/5/2021 |
Passed: Building - Slab |
|
Matt Forsyth |
3/11/2021 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
4/12/2021 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
4/12/2021 |
Failed: Building - Framing |
Need Gable End Adj. |
Matt Forsyth |
4/21/2021 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
4/21/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
4/21/2021 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
4/21/2021 |
Failed: Mechanical - Rough In |
Need Duct For Bath Fans |
Matt Forsyth |
4/21/2021 |
Passed: Building - Insulation |
Walls Only |
Matt Forsyth |
4/23/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
4/23/2021 |
Septic Release Inspection |
|
Health Dept |
6/4/2021 |
Failed: Electrical - Permanent Power |
Ground Rod Not Found |
Matt Forsyth |
6/9/2021 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
6/11/2021 |
Passed: Electrical - Permanent Power |
Need Driveway |
Matt Forsyth |
6/11/2021 |
Release to power company |
|
Melissa Garber |
6/16/2021 |
Cancelled: Building - Final |
|
Troy Crews |
6/17/2021 |
Passed: Building - Final |
Release Pending Blower Door Test And Lockout. |
Troy Crews |
6/25/2021 |
Certificate-Release Certificate |
|
Troy Crews |
6/29/2021 |