Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 223 SW QUIET CT
LAKE CITY, FL 32024
Parcel #: 03564-113
Acres: 8.26
Owner: Sparks, John & Shawna
Subdivision: Columbia Meadows
Zoning: A-3
Flood Zone: X
District: 5
Application #: 48260
Permit #: 000041369
Related Permit: Culvert Waiver: 000041370
Submitted: Tuesday, January 26, 2021
Issued: Tuesday, March 23, 2021
Expires: Wednesday, December 1, 2021
Completed: Wednesday, December 1, 2021
Status: Completed
Septic Release? Yes
Notes:
ENGINEER MINIMUM FINISHED FLOOR ELEVATION REQUIREMENT LETTER TO BE 85.30' INSTEAD OF ONE FOOT ABOVE THE ROAD. SEE ATTACHED LETTER. ADDITIONAL SURVEYOR CONFIRMATION LETTER NOW REQUIRED BEFORE NAILING INSPECTION. ELEVATION CONFIRMATION RECEIVED 86.64
Job Details
Elevation regulation Engineers Elevation Letter
Finished floor requirement 85.30'
Requirement needed By Nailing Inspection
Document needed is a Surveyor letter giving the Finished Floor Elevation
Document receieved Yes
Fema map number 12023C0395C
In floodway N
This is the construction of a Single Family Dwelling
Setbacks Front 30'
Setback Side 1 25'
Setback Side 2 25'
Setbacks Rear 25'
Stories 2
Heated Area (Sqft) 2291
Total Area (Sqft) 3450
Building Height 28
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Residential
Occupancy Use Title single family dwelling
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000) 21-0111
Review Notes
1/26/2021 Application pending.
1/26/2021 Point Review - Printed-Online Application
1/26/2021 Point Review - On Hold-Incomplete
1/26/2021 Point Review - Reviewed
1/27/2021 Zoning Review - Reviewed
1/28/2021 Plan Review - Reviewed
2/4/2021 Zoning Review - Reviewed
2/4/2021 Final Review - Documents Required
2/16/2021 Final Review - Payment Needed
2/22/2021 Permit Issued
3/23/2021 Permit reissued to reflect updated information.
7/27/2021 Final Review - Payment Needed
Contractors
Name/ Business License Title Role
Kevin L Bedenbaugh Jr
Plumb Level Construction Co Llc
CGC1516042 General Contractor Contractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Kevin L Bedenbaugh Jr
Plumb Level Construction Co Llc
CCC1329482 Roofing Contractor Subcontractor
Ryan C Beville
Rbi Electrical Contracting Llc
EC13004236 Electrical Contractor Subcontractor
Timothy D Shatto
Shatto Heating & Air, Inc.
CAC057875 A/c Class B Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Builder To Obtain Engineering Letter For Floor Level Troy Crews 3/4/2021
Passed: Engineering - Setbacks Troy Crews 3/4/2021
Passed: Plumbing/Gas - 1st Underground Rough–In Reminder Need Engineer Letter Before Slab, Also Need Surveyor Confirmation Letter To Match Engineer Prior To Nailing Inspection Troy Crews 3/18/2021
Passed: Building - Slab Troy Crews 3/24/2021
Passed: Building - Roof Decking Leave Porch Straps Open Next Inspection Troy Crews 4/12/2021
Passed: Building - Wall Sheathing Troy Crews 4/12/2021
Passed: Building - Strapping Troy Crews 4/16/2021
Passed: Building - Framing Bonus Room Not Approved As Sleeping Area Troy Crews 4/29/2021
Passed: Electrical - 2nd Rough-In Troy Crews 5/26/2021
Passed: Mechanical - Rough In Troy Crews 5/26/2021
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 5/26/2021
Passed: Plumbing/Gas - Tub Set/Shower Pan Troy Crews 5/26/2021
Failed: Building - Insulation Garage Walls Not Done Troy Crews 6/1/2021
Passed: Building - Insulation Sent Pictures Of Garage Walls Done Troy Crews 6/2/2021
Passed: Electrical - Permanent Power Need Septic Release. Troy Crews 7/27/2021
Release to power company Melissa Garber 8/17/2021
Septic Release Inspection Health Dept 8/17/2021
Failed: Building - Final Back Door Step Too Tall 9inches, Need Blower Door Test, Top Floor Stair Needs Handrail For Top Run Of Steps. Troy Crews 11/24/2021
Passed: Building - Final Troy Crews 12/1/2021