Permit Details

Permit Search

Permit

Mobile Home

453 SW BARON GLN
FORT WHITE, FL 32038

Permit #
000041218
Application #
48136
Status Completed
  1. Submitted Jan 11, 2021
  2. Issued Jan 29, 2021
  3. Expires Oct 6, 2021
  4. Completed Apr 9, 2021

Property

Parcel #
03752-406
Owner
Bullard-denune Investment Co.(karla Laguna-mh)
Acres
4.75
Subdivision
Southern Meadows Phase 1
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
87'
Requirement needed
By Permanent Power Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0390C
In floodway
N
Mobile Home is a:
Double Wide
Year Built
2021
Width (Ft.In)
28
Length (Ft.In)
56
Driveway access to home:
Private Drive
Septic #
21-0042
Setbacks Front
30'
Setback Side 1
25'
Setbacks Rear
25'
Dev Permit #
F023-
Setback Side 2
25'
Are you applying for a 5 year temporary permit?
No
Serial #
LOHGA20036473AB
Wind Zone?
2
Residential or Commercial Use?
Residential

Status & Review History

  1. Application pending.
  2. Zoning Review - Reviewed
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Zoning Review - Reviewed
  6. Plan Review - Reviewed
  7. Final Review - Payment Needed
  8. Point Review - Reviewed
  9. Permit Issued

Contractors

  • Brent M Strickland

    License
    IH1104218
    Title
    Mh Installer (ih)
    Role
    Contractor
  • Glenn Whittington

    Whittington Electric Inc

    License
    EC13002957
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Michael A Boland

    Ace A/c Of Ocala Llc

    License
    CAC1817716
    Title
    Cert Class B A/c
    Role
    Subcontractor

Inspections

  1. Jan 28, 2021

    Septic Release Inspection

    Inspected by Health Dept

  2. Apr 9, 2021

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  3. Apr 9, 2021

    Passed: Mobile Home - Mobile Home Set-Up Final

    Inspected by Anthony Aslan

  4. Apr 9, 2021

    Release to power company