Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
1/11/2021 |
Passed: Building - Slab |
|
Matt Forsyth |
1/14/2021 |
Passed: Building - Ext Strapping/Wall Sheathing |
Still Need Inspection On North End Bonus Room Wall For Nailing |
Matt Forsyth |
2/25/2021 |
Failed: Building - Ext Strapping/Wall Sheathing |
Need Strapping Lst30 Tieing Wall And Gable |
Matt Forsyth |
3/4/2021 |
Passed: Building - Ext Strapping/Wall Sheathing |
Strapping Completed |
Matt Forsyth |
3/10/2021 |
Passed: Building - Framing |
|
Matt Forsyth |
4/23/2021 |
Passed: Electrical - 2nd Rough-In |
Nail Plate Needed Bedrm4 |
Matt Forsyth |
4/23/2021 |
Failed: Mechanical - Rough In |
Need Exaustfan Duct In Toilet Room. Condensate Line Needs Nail Plate Laundry Rm |
Matt Forsyth |
4/23/2021 |
Failed: Plumbing/Gas - 2nd Rough-In |
Pex Piping In Top Of Wall On The Exterior Needs Pipe Insulation |
Matt Forsyth |
4/23/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
5/7/2021 |
Failed: Plumbing/Gas - 2nd Rough-In |
Item Was Not Taken Care Of On The Last Inspection Protection Of Water Pipe On Exterior Wall Top Plate |
Matt Forsyth |
5/7/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
Foam Insulation Will Be Used For Protection |
Matt Forsyth |
5/7/2021 |
Failed: Building - Insulation |
Installation Was Started But Not Finished |
Matt Forsyth |
5/21/2021 |
Passed: Building - Insulation |
|
Matt Forsyth |
5/25/2021 |
Septic Release Inspection |
|
Health Dept |
8/3/2021 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
9/8/2021 |
Release to power company |
|
Troy Crews |
9/8/2021 |
Passed: Building - Final |
|
Matt Forsyth |
11/23/2021 |