| Passed: Building - Footer |
|
Troy Crews |
12/21/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
12/21/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
12/31/2020 |
| Failed: Electrical - Temporary Service |
No Meter Can On Site |
Troy Crews |
12/31/2020 |
| Passed: Building - Slab |
|
Troy Crews |
1/4/2021 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
1/21/2021 |
| Passed: Building - Roof Decking |
|
Troy Crews |
1/21/2021 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
2/3/2021 |
| Release to power company |
|
Troy Crews |
2/3/2021 |
| Passed: Building - Framing |
|
Anthony Aslan |
2/22/2021 |
| Passed: Electrical - 2nd Rough-In |
Couple Of Light Boxes Hanging Out Of Ceiling. |
Anthony Aslan |
2/22/2021 |
| Failed: Plumbing/Gas - 2nd Rough-In |
Gas Pipe Has No Pressure |
Anthony Aslan |
2/22/2021 |
| Passed: Building - Wall Sheathing |
Windows |
Troy Crews |
3/5/2021 |
| Passed: Building - Insulation |
|
Troy Crews |
3/9/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
3/9/2021 |
| Passed: Electrical - Permanent Power |
Need Septic Final-- Rec'd 4/30 |
Troy Crews |
4/19/2021 |
| Release to power company |
|
Melissa Garber |
5/3/2021 |
| Septic Release Inspection |
|
Health Dept |
5/3/2021 |
| Failed: Building - Final |
Need Blower Door Test, Bath Exhaust Fans Missing Motors |
Anthony Aslan |
6/2/2021 |
| Passed: Building - Final |
|
Anthony Aslan |
6/3/2021 |