Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
Need Grounding Wire, Take Picture. |
Anthony Aslan |
1/5/2021 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
1/5/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
1/26/2021 |
Passed: Building - Slab |
|
Anthony Aslan |
2/5/2021 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
3/17/2021 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
3/17/2021 |
Passed: Building - Framing |
Some King Studs, Couple Straps |
Anthony Aslan |
3/22/2021 |
Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
4/1/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
4/1/2021 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
Partial Inspection, Shower Pan In Master Not Ready |
Anthony Aslan |
4/1/2021 |
Failed: Mechanical - Rough In |
Laundry Wall Needs To Be Furred To Allow For Deep Dryer Box, No Screws In Kitchen Exhaust Piping. Also Need King Studs Added In Master Closet Window. |
Anthony Aslan |
4/1/2021 |
Failed: Mechanical - Rough In |
Need Screws In Kitchen Exhaust Pipe |
Anthony Aslan |
4/5/2021 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Anthony Aslan |
4/5/2021 |
Cancelled: Mechanical - Rough In |
|
Anthony Aslan |
4/7/2021 |
Passed: Mechanical - Rough In |
Screws In Exhaust Piping Installed |
Anthony Aslan |
4/9/2021 |
Passed: Building - Insulation |
|
Anthony Aslan |
4/9/2021 |
Passed: Electrical - Permanent Power |
|
Anthony Aslan |
5/27/2021 |
Release to power company |
|
Anthony Aslan |
5/27/2021 |
Septic Release Inspection |
|
Health Dept |
6/2/2021 |
Release to power company |
Contractor Requested To Resend Because The Power Comp
didnt Receive. |
Anthony Aslan |
6/18/2021 |
Passed: Building - Final |
Front Porch Outlets Open Ground, Laundry Room Outlet Open Ground. |
Anthony Aslan |
8/11/2021 |