Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Troy Crews |
12/7/2020 |
Passed: Engineering - Setbacks |
Need Porta Pottie |
Troy Crews |
12/7/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
12/14/2020 |
Passed: Building - Slab |
|
Troy Crews |
12/21/2020 |
Passed: Building - Roof Decking |
|
Troy Crews |
1/7/2021 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
1/7/2021 |
Failed: Building - Framing |
Anchor Bolts Not Complete Call Back In With Rough In Inspections |
Troy Crews |
1/7/2021 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
1/7/2021 |
Release to power company |
|
Troy Crews |
1/7/2021 |
Passed: Building - Framing |
Items Completed |
Troy Crews |
1/20/2021 |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
1/20/2021 |
Failed: Mechanical - Rough In |
Need Seals On Flange Of All Registers, Oven Duct No Male Inside Connections In Vertical Piping To Catch Grease |
Troy Crews |
1/20/2021 |
Failed: Plumbing/Gas - 2nd Rough-In |
No Pressure Water Lines, No Nail Plates On Any Drain Lines |
Troy Crews |
1/20/2021 |
Failed: Building - Insulation |
Need Clearance For Triple-wall Fireplace Duct |
Matt Forsyth |
1/26/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
1/26/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/26/2021 |
Passed: Building - Insulation |
Phone Removed From Chimney Pipe And Replaced With Firewool |
Troy Crews |
1/27/2021 |
Septic Release Inspection |
|
Health Dept |
3/11/2021 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
3/23/2021 |
Release to power company |
|
Troy Crews |
3/23/2021 |
Passed: Building - Final |
Need Letter From A/c Contractor On Equipment Line Size And Warranty. |
Anthony Aslan |
5/4/2021 |
Certificate-Release Certificate |
Rec'd Hvac Letter |
Anthony Aslan |
5/11/2021 |