Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
12/14/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
12/14/2020 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
Test Stack Needs To Be On High End Of System |
Matt Forsyth |
1/11/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
1/11/2021 |
Failed: Building - Slab |
Missing #5 Bar In Garage Footing |
Matt Forsyth |
1/13/2021 |
Passed: Building - Slab |
#5 Bar In Continuous Footing For Garage |
Matt Forsyth |
1/13/2021 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
2/9/2021 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
2/9/2021 |
Failed: Building - Framing |
2 Windows Upstairs Need To Be Tempered Glass |
Matt Forsyth |
3/24/2021 |
Failed: Building - Strapping |
Strapping Was Covered Up With Finished Hardie Board |
Matt Forsyth |
3/24/2021 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
3/24/2021 |
Failed: Mechanical - Rough In |
Exhaust Fans In Bathrooms Were Not Installed |
Matt Forsyth |
3/24/2021 |
Failed: Plumbing/Gas - 2nd Rough-In |
Need Nail Plate For Top Of Wall For Gas Line On Exterior Wall |
Matt Forsyth |
3/24/2021 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
4/9/2021 |
Release to power company |
|
Matt Forsyth |
4/9/2021 |
Passed: Building - Insulation |
|
Matt Forsyth |
4/15/2021 |
Passed: Building - Framing |
|
Matt Forsyth |
4/15/2021 |
Passed: Building - Strapping |
|
Matt Forsyth |
4/15/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
4/15/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
4/15/2021 |
Septic Release Inspection |
|
Health Dept |
8/4/2021 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
8/11/2021 |
Release to power company |
|
Matt Forsyth |
8/11/2021 |
Failed: Building - Final |
House Needs To Be Finished,blower Door Test |
Matt Forsyth |
10/25/2021 |
Passed: Building - Final |
Check Front And Back Porch Plugs Make Sure Gfci Protected |
Troy Crews |
11/9/2021 |