Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
11/16/2020 |
Passed: Building - Footer |
|
Troy Crews |
11/20/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
11/20/2020 |
Passed: Building - Slab |
|
Troy Crews |
11/20/2020 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
1/5/2021 |
Passed: Building - Roof Decking |
|
Troy Crews |
1/5/2021 |
Passed: Building - Framing |
|
Troy Crews |
2/10/2021 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
2/10/2021 |
Failed: Plumbing/Gas - 2nd Rough-In |
Not Complete Nail Plates, Pressure On Lines, Shower Valve Etc. |
Troy Crews |
2/10/2021 |
Passed: Mechanical - Rough In |
Reminder Will Need Notice On Electric Panel For Air Handler In Attic |
Troy Crews |
2/10/2021 |
Passed: Building - Insulation |
|
Troy Crews |
3/1/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
Items Corrected |
Troy Crews |
3/1/2021 |
Failed: Electrical - Temporary Service |
Need Elevation Confirmation Letter From Surveyor, Need Septic Final From Health Dept., Need Final Inspection On Culvert From Public Works. |
Troy Crews |
3/24/2021 |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
5/18/2021 |
Septic Release Inspection |
|
Health Dept |
6/4/2021 |
Failed: Electrical - Temporary Service |
You Are Trying To Get Permanent Power, Need Driveway Inspection By Public Works, And Engineering Letter For Floor Elevation Approved |
Troy Crews |
6/7/2021 |
Release to power company |
|
Laurie Hodson |
6/8/2021 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
6/8/2021 |
Passed: Electrical - Permanent Power |
Need Final On Culvert Inspection For Release |
Troy Crews |
6/8/2021 |
Failed: Building - Final |
Need Air Handler Notice On Electric Panel Send Picture Of It Installed. |
Troy Crews |
6/24/2021 |
Passed: Building - Final |
Decal Installed For Air Handler |
Troy Crews |
6/25/2021 |