| Septic Release Inspection |
|
Health Dept |
10/15/2020 |
| Passed: Building - Footer |
|
Matt Forsyth |
10/28/2020 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
10/28/2020 |
| Passed: Building - Vertical Cells/Columns |
|
Matt Forsyth |
11/2/2020 |
| Passed: Building - Framing |
|
Matt Forsyth |
2/1/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
2/1/2021 |
| Passed: Mechanical - Above Ceiling |
Mini Split |
Matt Forsyth |
2/1/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
2/1/2021 |
| Passed: Building - Insulation |
|
Anthony Aslan |
2/8/2021 |
| Passed: Electrical - Permanent Power |
Co Not Paid
payment Rec'd. |
Anthony Aslan |
3/16/2021 |
| Release to power company |
|
Melissa Garber |
3/18/2021 |
| Passed: Building - Final |
Need Bdt |
Anthony Aslan |
10/20/2021 |