Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
|
Troy Crews |
10/28/2020 |
Release to power company |
|
Troy Crews |
10/28/2020 |
Passed: Building - Footer |
|
Troy Crews |
11/20/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
11/20/2020 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
Not Complete |
Troy Crews |
12/7/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
12/8/2020 |
Passed: Building - Slab |
|
Troy Crews |
12/9/2020 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
12/23/2020 |
Passed: Building - Framing |
|
Troy Crews |
1/11/2021 |
Passed: Building - Roof Decking |
|
Troy Crews |
1/11/2021 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
1/22/2021 |
Failed: Mechanical - Rough In |
Not Complete |
Troy Crews |
1/22/2021 |
Failed: Plumbing/Gas - 2nd Rough-In |
Check For Nail Plates |
Troy Crews |
1/22/2021 |
Passed: Mechanical - Rough In |
|
Troy Crews |
1/25/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
1/25/2021 |
Passed: Building - Insulation |
|
Troy Crews |
2/2/2021 |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
2/23/2021 |
Release to power company |
|
Laurie Hodson |
4/5/2021 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
4/5/2021 |
Passed: Electrical - Permanent Power |
Need Driveway Release, Need Septic Release |
Anthony Aslan |
4/5/2021 |
Septic Release Inspection |
|
Health Dept |
4/5/2021 |
Cancelled: Building - Final |
|
Melissa Garber |
4/12/2021 |
Rescheduled 4/15/2021:Building - Final |
|
Anthony Aslan |
4/14/2021 |
Passed: Building - Final |
Garage Doors Not Installed. Bonus Room Not Finished Out. |
Anthony Aslan |
4/15/2021 |