Inspection |
Notes |
Performed By |
Date |
Failed: Engineering - Final Driveway |
Needs To Install Culvert, Needs To Get Culvert Permit. |
Mccormick, David |
10/12/2020 |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
10/12/2020 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
10/14/2020 |
Release to power company |
|
Troy Crews |
10/14/2020 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
Fill Waste Lines Complete, Need Test On Cpvc Lines Under Slab |
Troy Crews |
11/17/2020 |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
11/18/2020 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
Waste Lines Not Full Of Water, No Pressure On Water Lines For Test. |
Troy Crews |
11/18/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
11/18/2020 |
Passed: Building - Footer |
|
Troy Crews |
11/19/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
11/19/2020 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
11/19/2020 |
Rescheduled 1/26/2021:Building - Framing |
|
Troy Crews |
1/25/2021 |
Rescheduled 1/26/2021:Building - Roof Decking |
|
Troy Crews |
1/25/2021 |
Rescheduled 1/26/2021:Building - Strapping |
|
Troy Crews |
1/25/2021 |
Rescheduled 1/26/2021:Building - Wall Sheathing |
|
Troy Crews |
1/25/2021 |
Passed: Building - Framing |
Check Anchor Bolts Next Inspection |
Troy Crews |
1/26/2021 |
Passed: Building - Roof Decking |
|
Troy Crews |
1/26/2021 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
1/26/2021 |
Passed: Building - Strapping |
|
Troy Crews |
1/26/2021 |
Passed: Building - Roof Decking |
Peel And Stick Installed |
Troy Crews |
1/27/2021 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
2/24/2021 |
Failed: Mechanical - Rough In |
One Register Pulled Loose, All Registers And Return Boxes Need Seal For Drywall |
Troy Crews |
2/24/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
2/24/2021 |
Failed: Mechanical - Rough In |
Register Still Loose, Also Need Drywall Seals On All Registers And Return Box |
Troy Crews |
2/26/2021 |
Passed: Mechanical - Rough In |
Items Corrected |
Troy Crews |
3/1/2021 |
Passed: Building - Insulation |
Dryer Pipe Needs Nail Plates Prior To Drywall Installation. |
Anthony Aslan |
3/5/2021 |
Passed: Electrical - Permanent Power |
Need Final Culvert Inspection 386-7581019 Also Need Final Septic 758-1058 |
Troy Crews |
10/1/2021 |
Septic Release Inspection |
|
Health Dept |
10/4/2021 |
Failed: Engineering - Final Driveway |
Pipe Is Not 32 Feet As Required. Mitered Ends Have Not Been Poured . There Is Not 4 Inches Of Suitable Material On Top Of Pipe. |
Jones, Richard |
10/6/2021 |
Cancelled: Electrical - Permanent Power |
|
Melissa Garber |
10/6/2021 |
Release to power company |
|
Melissa Garber |
11/1/2021 |
Passed: Engineering - Final Driveway |
|
Jones, Richard |
11/1/2021 |
Failed: Building - Final |
Need Locking Caps On Condenser, Front Porch Gfci Missing Outlet Cover |
Anthony Aslan |
11/19/2021 |
Passed: Building - Final |
Corrections Made |
Anthony Aslan |
11/22/2021 |