Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
10/1/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
10/1/2020 |
Cancelled: Electrical - Temporary Service |
|
Matt Forsyth |
10/1/2020 |
Failed: Electrical - Temporary Service |
Need Dead Cover For Service |
Matt Forsyth |
10/14/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Laundry Trap Under The Slab |
Matt Forsyth |
10/14/2020 |
Cancelled: Building - Slab |
|
Melissa Garber |
10/15/2020 |
Cancelled: Building - Slab |
|
Melissa Garber |
10/15/2020 |
Cancelled: Building - Slab |
|
Melissa Garber |
10/15/2020 |
Passed: Building - Slab |
|
Troy Crews |
10/16/2020 |
Passed: Building - Lintel/Tie Beam |
|
Matt Forsyth |
10/23/2020 |
Failed: Electrical - Temporary Service |
Not Approved Dead Cover |
Matt Forsyth |
10/30/2020 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
11/13/2020 |
Release to power company |
|
Matt Forsyth |
11/13/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
11/25/2020 |
Passed: Building - Framing |
|
Matt Forsyth |
1/20/2021 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
1/20/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
1/20/2021 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
1/20/2021 |
Passed: Building - Insulation |
|
Matt Forsyth |
1/27/2021 |
Septic Release Inspection |
|
Health Dept |
3/11/2021 |
Failed: Electrical - Permanent Power |
Locking Hasp On Electric Panel |
Matt Forsyth |
4/16/2021 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
5/10/2021 |
Release to power company |
|
Matt Forsyth |
5/10/2021 |
Failed: Building - Final |
Need Blower Test, Open Ground Wash Outlet, Final Termite Spray |
Anthony Aslan |
6/3/2021 |
Passed: Building - Final |
Blower Door, And Termite Received, Plug Checked By Electrician Per Owner. |
Troy Crews |
6/11/2021 |